Click here for PDF version of this Order (300 KB)
![](../../../images/iraclogo-n207.gif)
Docket UE20711
Order No. UE04-02
IN THE MATTER
of an
application by Maritime Electric Company, Limited for approval to purchase and
install a 50 megawatt combustion turbine generator at the Company's
Charlottetown generating station.
BEFORE THE COMMISSION
on Monday, the 9th day of August, 2004.
Maurice Rodgerson, Acting
Chair
Weston Rose, Commissioner
James Carragher, Commissioner
George MacDonald, Commissioner
Order
Contents
Appearances & Witnesses
Reasons for Order
1.
Introduction
2.
Background
3.
Application, Interventions & Submissions
4.
Discussion & Findings
4.1
Introduction
4.2
The
Need for Capacity
4.3
Capacity Options and the Proposed Combustion Turbine
5.
Other
Matters
6.
Disposition
Order
Appearances & Witnesses
For
Maritime Electric Company, Limited:
Counsel:
William G. Lea. Q.C. & Spencer Campbell
Witnesses:
James A. Lea, President & Chief Executive Officer
John Gaudet, Vice-President, Operations
Robert Younker, Director of Planning
For
the Government of Prince Edward Island:
Counsel: Mark Campbell
Witnesses:
Wayne MacQuarrie, Chief Executive Officer
Prince Edward Island Energy Corporation
Mike Proud, Energy
Officer
Department of Environment & Energy
For Cavendish Farms:
Witness:
Scott Smith, Operations Manager
For Himself:
Witness:
Leo Broderick
For the Island Regulatory
& Appeals Commission:
Counsel:
Thomas A. Matheson, Q.C.
Witness (on behalf of
Commission staff):
Terry MacDonald, KnAP Energy Consultants
Staff:
Donald G. Sutherland, Director, Technical & Regulatory Services
Kay Ross, Recording Secretary
Reasons for Order
1.
Introduction
[1] This is an application by Maritime Electric Company, Limited ("Maritime Electric", the
"Company" or the "Utility") for approval to purchase and install a 50 megawatt
("MW") combustion turbine generator at the Company’s Charlottetown generating
station. The application was heard by the Commission at public hearings
conducted in Charlottetown on July 20, 2004 to July 23, 2004 after due public
notice.
[2]
Formal interventions in this matter were filed by the Government of Prince Edward
Island as represented by the Minister of Environment and Energy (the
"Government of PEI" or "Government"), Cavendish Farms and by Emera Inc. ("Emera"). The Government participated in the hearing process and submitted
evidence and argument. Cavendish Farms appeared and made a presentation at the
hearing. Emera did not participate in the hearing process.
[3]
The Commission heard, as well, from Terry MacDonald, an expert in generation planning who was retained
by Commission staff to review and comment on the application. The Commission
also heard from Leo Broderick, a member of the public, and received a written
submission from P.E.I. Energy Systems.
[4] The Commission acknowledges
these submissions and acknowledges, as well, the assistance of counsel for the
parties and the evidence of each of the witnesses.
2 .
Background
[5]
In the fall of 2003, the
Legislative Assembly of Prince Edward passed amendments to the former
Electric Power and Telephone Act establishing a new
Electric Power Act
(the "Act") and returning the Company to the full jurisdiction of the
Commission. Section 17 of the Act reads, in part, as follows:
Capital budget of public utility |
17.
(1) Every public utility shall, at such date as the Commission
determines, submit to the Commission for its approval an annual capital
budget of proposed improvements or additions to the property of the
public utility for the ensuing calendar year, being property of the
utility employed in the provision of a service that is subject to the
jurisdiction of the Commission under this Act.
|
Ongoing expenditures |
(2) The budget shall contain an estimate of future required expenditures
on any improvements or additions to the property of the public utility
that will not be completed in the ensuing calendar year.
|
Approval of Commission |
(3) The Commission, may, after reviewing the annual capital budget of a
public utility and on such terms and conditions as it may prescribe
approve in whole or in part the annual capital budget of proposed
improvements or additions to the property of the public utility.
|
Report of actual expenditures |
(4) Every public utility shall submit for the approval of the Commission
a report on its actual expenditures on improvements or additions to its
property in the prior calendar year together with an explanation as to
expenditures in excess of those approved under subsection (1) within
sixty days of the calendar year end.
|
[6]
The application before the Commission is part of
the Company’s capital budget. It reflects the Company’s view on what is
required to satisfy the utility’s public service mandate. That mandate is set
out in Section 3 of the Act:
Duties of public
utilities |
3.
Every public utility shall |
|
(a) furnish at all times such reasonably safe and adequate service and
facilities for services as changing conditions require;
|
|
(b) construct its lines with poles of such height as the Commission may
prescribe having regard for the nature of the line and the voltage of
the electric current passing through the same. |
[7]
It is well accepted that public utilities
must meet their public service mandate at the lowest possible cost. Maritime
Electric submits that the proposal before the Commission satisfies the
Utility’s statutory duty to serve obligation at the lowest overall cost.
3 .
Application, Interventions & Submissions
[8]
The Company’s proposal involves the design,
construction and commissioning of a 50 MW combustion turbine generator at the
Utility’s Charlottetown generating station and involves capital expenditures
estimated at $6 million in 2004 and $29 million in 2005. According to the
Company, the proposal will provide the following benefits:
1.
It is a less
expensive approach for the electricity consumers of PEI than the other option
open to Maritime Electric – increasing the capacity of the interconnection
immediately.
2.
It will defer the
installation of a third cable to the mainland. Without additional on-Island
generating capacity, a third cable would be needed to ensure system
reliability.
3.
It will provide 50 MW
of installed generating capacity. Currently, Maritime Electric needs to
purchase MW of capacity, which is being done on a short-term basis.
4.
It will enhance
security of supply. During 2003 NB Power has indicated that the amount of
capacity it has available to sell to Maritime Electric may be reduced
beginning in Fall 2005.
5.
It will provide
flexibility in the face of uncertainty. Initially the combustion turbine will
operate on light fuel oil as a peaking unit. If natural gas becomes available,
the combustion turbine could be converted to operate on natural gas and
integrated into a combined cycle operation with one of the existing steam
turbine generating sets at the Charlottetown Plant.
[Ex. A-1, p. 7-1]
[9]
The Company estimates that the proposal will
result in an overall rate increase of approximately 4%.
[10]
The Government of P.E.I. submits that the Company
has not fully explored all of the alternatives available to it. The Government
submits, as well, that staff’s independent witness has similarly not explored
all available alternatives. It suggests that there are viable alternatives to
the Company’s proposal that would result in overall long-terms savings to the
consumer. The Government asks that Maritime Electric be directed by the
Commission to carry out further analyses before any decision is made on the
specific proposal before the Commission.
[11]
Cavendish Farms opposes the Utility’s proposal.
It suggests, among other things, that the Company has not adequately examined
alternative means of low cost and reliable energy. According to Cavendish
Farms’ Scott Smith:
It is our opinion that
Maritime Electric has failed to demonstrate they have developed a plan that is
in the best interests of rate payers in either the short or the long term. The
plan submitted to the Commission raises many concerns and needs further
scrutiny. My cursory review of this subject has only scratched the surface of
the many unanswered questions with this proposal. Committing to the capital
cost is a significant investment for future rate payers and it should be given
serious consideration by the Commission. Additionally, the operational costs
will likely become the burden of the rate payer for the life of the plant.
Recent rate increases have put an unfair and unnecessary burden on the rate
payer while the regulatory structure fails to encourage innovation, efficiency
and energy security. The proposed plan provided by Maritime Electric will
raise electrical rates even further creating a greater loss of competitive
position between Island companies and our competitors outside the province.
The plan submitted by the utility would appear not to consider many issues and
factors that could have additional adverse effect on electrical rates. It is
our concern that Maritime Electric will be granted approval for this plant
then return to the Commission to seek even further rate increases to cover
fuel, capital and operational costs at a later date that have not adequately
been addressed in this proposal. I acknowledge the nature of the regulatory
model used by this Commission is not totally within your control, but we
encourage you to seek out a regulatory structure that achieves greater balance
between the requirement to have a profitable utility but also protects
customers from further unwarranted rate increases. Mechanisms are required to
place the burden of risk and cost with the utility for the planning,
construction and operation of facilities.
[Ex. O-2, p.
7]
[12]
Leo Broderick gave evidence opposing the
application. He made a number of suggestions concerning public ownership of
Maritime Electric and testified that Prince Edward Island must pursue a
renewable energy strategy.
[13]
Terry MacDonald was engaged on behalf of
Commission staff to carry out an independent evaluation of the Company’s
proposal. Mr. MacDonald prepared a two-volume report of his assessment and
gave evidence at the hearing. Mr. MacDonald’s assessment contains the
following conclusions:
·
The [Maritime
Electric] load is growing and the load forecast is not unreasonable and should
be accepted.
·
Additional
capacity is required by 2005 so as to maintain an adequate level of planning
reserves.
·
Some
reinforcement of the electricity supply for P.E.I. is necessary before the
2006 peak to satisfy the single contingency criterion for the cable system.
·
[Maritime
Electric] has assessed the reasonable options – on Island generation and cable
reinforcement with off Island capacity purchases.
·
The cable option
with purchased capacity requires that new transmission be built in New
Brunswick. The source of any purchased capacity is not apparent. The cost of
using the transmission of [NB Power] and perhaps other systems may not be
adequately captured in the purchase option.
·
The only on
Island options that will meet reliability requirements and that are reasonable
in the circumstances are light oil fired combustion turbines.
·
The proposed 50
MW CT satisfies all of the planning criteria, including having the lowest long
term costs and it is doable in time to satisfy the needs.
[Ex. I-3, p.
9-1]
[14]
The Commission also received a written submission
from P.E.I. Energy Systems seeking a capacity credit for installed
cogeneration facilities. The Commission notes that this matter is more
properly addressed when Maritime Electric’s rates are reviewed later this
year. P.E.I. Energy Systems is encouraged to participate in the rate
proceedings.
4. Discussion & Findings
4.1
Introduction
[15]
The application before the Commission involves an
assessment of a number of issues. These issues can, however, be summarized as
follows:
1. whether there is
a need for additional capacity; and
2. if the need is established, whether the specific proposal of Maritime Electric address the Utility’s mandate of providing safe and adequate service at the lowest
possible cost.
4.2
The Need for Capacity
[16]
The evidence of Maritime Electric is that it
requires the replacement of 50 MW of system capacity that it currently
purchases via contract from NB Power. According to the Company, the
replacement capacity is required by November 1, 2005.
[17]
Under the current Interconnection Agreement
with NB Power, Maritime Electric is required to maintain a 15% planning
reserve. Mr. MacDonald noted in his evidence that, in terms of systems
reliability requirements, the Company follows conventional operating reserve
criteria for generation and a conventional single contingency criterion for
transmission.
[18]
A review of the Company’s evidence and
submissions, including its responses to the information requests of Mr.
MacDonald and the evidence of Mr. MacDonald, himself, establish to the
satisfaction of the Commission that additional capacity is required in the
fall of 2005 to enable the Company to satisfy planning reserve criteria. The
system reliability requirements described above are, in the Commission’s view,
generally accepted industry standards that must be maintained. They define, at
a high level, the safety and adequacy requirements of the Electric Power
Act.
[19]
The Commission therefore finds that additional
generating capacity is required. We turn our attention, then, to the level and
type of capacity required.
4.3
Capacity Options and the Proposed
Combustion Turbine
[20]
In its detailed
evaluation of capacity options, the Company reviewed a number of options and
narrowed its focus to two alternatives:
-
the installation of the proposed 50 MW combustion turbine; and
-
an expansion of the capacity of the interconnection with
New Brunswick and the continued
purchase of 50 MW of generating capacity.
[21] In his report to the Commission, Commission staff witness, Mr. MacDonald, prepared an
independent assessment of alternatives, including the proposal of the Company
as well sources such as wind, biomass, coal, nuclear, orimulsion and gas,
among others.
[22]
The Company submits that the proposed combustion
turbine is preferable for the following reasons:
·
It has
a lower present value cost than expanding the capacity of the interconnection
with New Brunswick and continuing to purchase 50 MW of generating capacity.
·
Installing on-Island generating capacity will enhance security of supply by
reducing the need to purchase generating capacity.
·
It
will maintain Maritime Electric’s flexibility to benefit from the use of
natural gas if it becomes available in PEI.
[Ex. A-1, pp.
1-2 & 1-3]
[23]
In his
evidence, Mr. MacDonald, commented as follows:
There
are several uncertainties associated with the short term demand supply balance
in the Maritimes, the potential for changes in the pricing of transmission
services due to the evolution of the electricity market restructuring, the
fuel supply to Coleson Cove, the life of Pt. Lepreau and the availability and
price of natural gas.
One
must be aware that in competitive markets price volatility is a reality. When
commodities are scarce the price goes up. During January of 2004, when power
demand was high, marginal prices varied by a factor of almost fifty. The high
prices of January 2004 are not indicative of a market with a large capacity
surplus.
Merchant generators seek to maximize their return and they rightly price their
product accordingly. What this would imply for a long term capacity purchase
is a price based on the alternatives that the merchant generators or brokers
perceive a potential customer might have. This of course would be the
principal subject of negotiations.
The CT
[combustion turbine] option is entirely consistent with the newly released PEl
Energy Policy. Wind generation by its nature is intermittent, requiring
capacity back up. Locally based generation adds to security and adequacy.
Given
the foregoing, even if the present value of the costs of the two alternatives
(CT or cable) were the same, the certainty and security arising from
additional on Island generation would weigh in the selection of that option.
In the
circumstances the CT option is more cost effective than the cable alternative
as has been demonstrated in the evidence.
[Ex. I-3, p.
5-6]
[24]
Both the Government of P.E.I.
and Cavendish Farms take the position that Maritime Electric has not
adequately reviewed alternatives. In its assessment of the Company’s proposal,
the Government took the rather unusual move of obtaining its own quotes from
potential suppliers for short-term capacity and offered this as evidence that
the Company had not thoroughly analyzed all of the options available to it. It
carried out, as well, its own analysis of the costs of the third cable option.
That analysis—prepared by a local electrical engineering firm and included in
the written evidence of the Government—suggested, among other things, that
certain expenses quoted by Maritime Electric in the Company’s assessment of
the third-cable options were overstated.
[25]
The Government, as well,
suggested that Commission staff’s independent witness did not fully assess
available alternatives. Cavendish Farms suggests that the work of the
independent witness failed to shed any
light on the issues.
[26]
On this latter point, the
Commission is of the view that the assessment carried out by Mr. MacDonald is
both comprehensive and compelling. The work of Mr. MacDonald spanned several
months and resulted in an extensive two-volume report that, in our view,
represents a thorough assessment of the issues before us.
[27]
In the case of the
submission of Government, the Commission received a limited submission as well
as a copy of a quote from a turbine manufacturer and what appears to be a
portion of a copy of a report from a local electrical engineering firm on the
cost of a third-cable option. The Government suggests that the proposed
generator would expose Maritime Electric’s ratepayers to increases in costs
over the lifetime of the proposed unit that might otherwise be mitigated by
acquiring short-term capacity pending the construction of new base load
generation in the region.
[28]
According to Government:
By proceeding with the
Project, Maritime Electric will be asking ratepayers to pay an additional 3.9%
on their electricity bills for the next 30 years, the anticipated life and
amortization of the facility.
The Province submits that
a 30 year solution is not appropriate to address a short-term (5 year)
problem. A short-term problem should be addressed by a short-term solution.
The Province submits that
approval for the combustion turbine project at this time is premature given
that the Maritime Region will be required to build new generation or access
additional capacity from outside the region prior to 2008/09.
Maritime Electric’s
proposed schedule for constructing the combustion turbine project has now
missed some critical milestone dates. As a result, it would appear that
Maritime Electric will be required to make alternative arrangements to
purchase capacity for 2005.
As alternative
arrangements may be required, these arrangements should be extended through to
2007 when firmer regional decisions will be made regarding new baseload
capacity.
The Province submits that
Maritime Electric has not fully demonstrated that the Project, when compared
to other options that would maintain system reliability, does so at a lower
cost and provides a reduced impact to ratepayers over the 30 year lifespan of
the Project.
[Ex.
G-7, pp. 2-3 (references omitted)]
[29]
In its evidence, Government
proposed a number of alternatives, including:
-
the acquisition of capacity from other markets through existing
or proposed transmission infrastructure;
-
on-Island solutions, including the short-term
lease of generating units pending regional decisions on new generation;
and
-
recognition of wind generation as capacity.
[30]
The Government
noted, as well, that the P.E.I. Energy Corporation has interest in installing
generating units in conjunction with its existing wind generation if the
economics appear viable.
[31]
During the
course of the hearing, each of the alternatives proposed by the Government of
P.E.I. was discussed in some detail. In the case of the acquisition of
capacity from other markets, both the nature of the submission and the
responses to it by both Maritime Electric and the independent witness lead us
to the conclusion that the suggested alternatives are either:
1. inaccessible; or
2. unable to satisfy the legislative requirements or the terms of
the Interconnection Agreement with NB Power.
[32]
In the case of
on-Island solutions and the recognition of wind generation as capacity, the
evidence discloses that, in the case of wind power, it is not, as yet,
recognized as capacity by the Northeast Power Coordinating Council ("NPCC"), a
region of the North American Electric Reliability Council. Maritime Electric
and other utilities in the Maritime Provinces are part of the NPCC and are
interconnected with the North American power grid.
[33]
The fact that
wind power is not recognized as capacity by the NPCC effectively means that
Maritime Electric cannot, itself, claim that capacity in its arrangements with
NB Power and NPCC members. Requiring Maritime Electric to recognize wind power
as capacity would only require the replacement of that capacity with other,
more conventional sources. With the capacity factor noted in the evidence, the
Company is encouraged to advance the proposition with NPCC that wind power
should be given capacity recognition. For now, however, such recognition is
beyond the capability of the Company.
[34]
On the
remaining suggestion that short-term lease arrangements for on-island
generation are available, the Commission is of the view that the proposals
advanced by the Government lacked specificity. During the course of the
hearing, James Lea, the Company’s President and Chief Executive Officer,
testified on the costs that would be incurred if Maritime Electric was found
to be capacity deficient under the terms of the Interconnection Agreement
with NB Power. The Company submitted that, without additional generation, it
will likely find itself in that position in the fall of 2005.
[35]
Based on the
evidence and the submissions of the parties, the Commission has determined
that, if arrangements for suitable replacement capacity are not satisfactorily
concluded, Maritime Electric will not be able to satisfy the requirements of
the Interconnection Agreement with NB Power. Any resulting capacity
deficiency charges will result in higher costs to consumers.
[36]
In the case of
the overall position of the Government, the Commission finds that the
proposals are inconsistent with generally accepted planning and power system
reliability standards. In making this finding, the Commission is cognizant of
the critical role that electric power plays in the economy of Prince Edward
Island and the absolute duty of Maritime Electric to meet the needs of its
customers. There was no evidence presented to us that any of the suggested
alternatives would be less costly than the proposed combustion turbine. In
these circumstances—with a demonstrated capacity shortfall looming and the
lack of fully costed alternatives on the part of Government—the Commission is
simply unable to expose the Utility’s customers to the significant risks
associated with a further delay in proceeding with a necessary capacity
addition.
[37]
In the case of
the presentation of Cavendish Farms, we believe that many of the issues raised
were canvassed during the hearing. The Commission acknowledges the impact the
proposal will have on all ratepayers and is sympathetic to the economic impact
any rate increase will have on profitability. We reject, however, the
suggestion that available capacity alternatives have not been fully
considered.
[38]
In the
Commission’s view, the proposal of Maritime Electric will benefit Maritime
Electric’s customers a number of ways:
1. it will enhance security of supply in Prince Edward Island and
will be available to supply power within minutes of start-up;
2. it will meet current system availability requirements;
3. it will satisfy the terms of the interconnection agreement with
NB Power and will enable Maritime Electric to continue to purchase
interruptible energy from mainland sources; and
4. it is the lowest cost of the available alternatives and is a
long-term cost-effective solution to an ongoing capacity issue in
Prince Edward Island and the region.
[39]
In the final
analysis, the Commission has determined that the proposed capacity addition is
essential to the ongoing maintenance of necessary system reliability levels
and represents the lowest overall cost to the ratepayers of Maritime Electric.
Having fully considered the submissions of the parties and the applicable law,
the Commission finds that the proposed 50 MW combustion turbine is necessary
for the provision of safe and adequate service and facilities for services as
changing conditions require.
5 .
Other Matters
[40]
In accordance with a recommendation of staff’s
independent witness, the Commission will require Maritime Electric to file a
monthly status report on the combustion turbine project. The monthly report is
to outline the project progress, including an estimate of the in-service date,
expenditures and expenditure commitments and the forecast final cost. This
reporting requirement is to commence immediately.
6 .
Disposition
[41]
An order will therefore issue approving the
proposed 50 MW combustion turbine generator proposed by the Company.
IN THE MATTER
of an
application by Maritime Electric Company, Limited for approval to purchase and
install a 50 megawatt combustion turbine generator at the Company's
Charlottetown generating station.
Order
WHEREAS,
by application filed with the Commission on February 3, 2004, Maritime
Electric Company, Limited ("Maritime Electric") applied for approval of capital
expenditures to be made in 2004 and 2005 for the design, construction and
commissioning of a 50 MW combustion turbine generator to be located at the
site of Maritime Electric’s Charlottetown generating station;
AND WHEREAS
the Commission heard the application at public hearings conducted in
Charlottetown on July 20th, 21st, 22nd and 23rd, 2004;
AND UPON
considering the application
as well as the evidence adduced and the submissions of counsel;
NOW THEREFORE,
for the reasons given in the annexed Reasons for Order;
IT IS ORDERED
THAT
-
the application is approved at an overall estimated cost of $35 million;
-
Maritime Electric shall file with the Commission, on a monthly basis, a report
outlining the progress of the project, an estimate of the in-service date,
expenditures and expenditure commitments and the forecast final cost; and
-
the reporting requirement under 2 above is to commence
immediately.
DATED
at Charlottetown, Prince Edward Island, this 9th day of
August 2004.
BY THE COMMISSION:
Maurice Rodgerson, Chair
Weston Rose, Commissioner
James Carragher, Commissioner
George MacDonald, Commissioner
Notice:
Section 12 of the
Island Regulatory and Appeals Commission Act
reads as follows:
12.
The Commission
may, in its absolute discretion, review, rescind or vary any order or decision made by it
or rehear any application before deciding it.
Parties to this proceeding seeking a review of the
Commission's decision or order in this matter may do so by filing with the Commission, at
the earliest date, a written Request for Review,
which clearly states the reasons for the review and the nature of the relief sought.
Sections 13.(1) and 13(2) of the
Act
provide as follows:
13.(1)
An appeal lies
from a decision or order of the Commission to the Appeal Division of the Supreme Court
upon a question of law or jurisdiction.
(2)
The appeal shall be
made by filing a notice of appeal in the Supreme Court within twenty days after the
decision or order appealed from and the Civil Procedure Rules respecting appeals apply
with the necessary changes.
|