Click here for a PDF version of
this Order.
Docket UE21007
Order No. UE06-04
IN THE MATTER
of an application by Maritime Electric Company, Limited for
approval of a 39 MW Wind Power
Purchase Agreement.
BEFORE THE COMMISSION
on Tuesday, the 22nd day of
August, 2006.
Maurice Rodgerson, Chair
Weston Rose, Commissioner
James Carragher, Commissioner
Anne Petley, Commissioner
Order
CONTENTS
REASONS FOR ORDER
1.
Introduction
2.
Background
3. Procedure
4.
Discussion
& Findings
5.
Disposition
ORDER
Reasons for Order
1.
Introduction
[1] This is
an application
by Maritime Electric Company, Limited (the "Applicant", "Maritime Electric" or
the "Company") for an order or orders of the
Island Regulatory and Appeals Commission (the "Commission") approving a wind
power purchase agreement ("Agreement" or "WPPA") with the Prince Edward
Island Energy Corporation, a provincial crown corporation established under
the Energy Corporation Act, R.S.P.E.I. 1988 Cap. E-7 ("PEI Energy
Corporation") and the Government of Prince Edward Island ("Government of
PEI"). The agreement covers the purchase of 39 megawatts ("MW") of wind
power.
[2] The application
in this matter was filed on April 6, 2006 and publicly noticed in the
Province's daily newspapers and on the Commission's website. In response to
the notice, the Commission received a formal intervention from the Prince
Edward Island Power Company Limited ("PEI Power"). There were no other
comments or responses to the Commission's public notices.
2.
Background
[3]
In 2004,
the Government of PEI announced an
Energy Framework and Renewable Energy
Strategy
1. Its
stated purpose is described as follows:
. . . to ensure that residents of Prince
Edward Island have access to secure and competitively priced energy
supplies, which are acquired and consumed in an efficient and
environmentally responsible manner . . .
2
[4] The
Energy Framework and Renewable Energy Strategy establishes a Renewable
Portfolio Standard, or RPS, for electricity of at least 15 per cent by
2010. The RPS requirement has since been incorporated into the
Renewable
Energy Act, S.P.E.I., 2005, Cap. R-12.1, section 3(1) of which reads as
follows:
3. (1) For the calendar year beginning on
January 1, 2010 and for each calendar year thereafter, every public utility
shall obtain at least 15 percent of the total amount of electric energy that
it sells during that calendar year from renewable energy sources.
[5]
Presently, the PEI Energy Corporation has approximately 13 MW of wind power
installed at North Cape, Prince Edward Island and sells the energy to
Maritime Electric. This represents approximately four per cent of the
Island's current electricity needs. Using a 38% annual capacity factor,
Maritime Electric anticipates that an additional 39 to 40 MW of renewable
energy will be required to meet the requirements of the
Renewable Energy
Act.
[6] The
Agreement under consideration here states that the PEI Energy Corporation is
undertaking the development of a 30 MW wind farm at East Point, Prince
Edward Island and that it has the right to sell wind power produced at a
nine MW wind farm to be developed by Ventus Energy Inc. ("Ventus") at
Norway, Prince Edward Island. According to documents on file, Ventus is an
investor-owned company that develops wind power projects. With the 39 MW of
wind power covered under the proposed Agreement, Maritime Electric will
essentially meet the RPS requirements of the
Renewable Energy Act.
[7] The
intervention filed in this matter by PEI Power alleges, among other things,
that the proposed WPPA is not the least costly alternative available to
Maritime Electric to meet the requirements of the
Renewable Energy Act. In
addition, PEI Power objects to the process, or lack thereof, used by
Maritime Electric in sourcing renewable energy at the lowest cost. PEI Power
asks that the Commission:
3.
Procedure
[8] As noted
above, PEI Power seeks a public hearing. The Commission has decided against
an oral hearing in favour of a written hearing that fully considers the
relevant issues.
[9] In
Commission Order
PC05-01, dated December 15, 20053,
the Commission commented on a similar request for an oral hearing. The
comments in Order PC05-01 have relevance here:
[9] The principles of natural justice
have developed in administrative law to provide a party with an interest in
a proceeding with an opportunity to be heard before a decision contrary to
that interest is made. Over time, the principles of natural justice have
evolved into a general duty of procedural fairness which is owed by an
administrative tribunal to those potentially affected by its decisions.
[10] In general terms, the duty of
fairness requires that the tribunal, or decision maker, give notice to
interested participants about a decision it is contemplating, as well as
disclosure of information that is relevant to the issue. The participants
should then be provided with an opportunity to present evidence or argument
or both. The steps that are required by a tribunal to fulfill the duty of
procedural fairness vary with the specific context of each case and all of
the circumstances must be considered in order to consider the context of the
duty.
[11] The Supreme Court of Canada has made
it clear that the right to participate in the decision-making process does
not automatically mean that a party has a right to an oral or a public
hearing. A leading case on procedural fairness is Baker v. Canada (Minister
of Citizenship and Immigration), [1999] 2 S.C.R. 817, a decision of the
Supreme Court of Canada where the court held, among other things, that a
decision, by itself, not to hold a hearing is not a denial of fair
procedure. The court stated that a number of factors should be considered,
including the governing legislation and the factual circumstances of the
matter under consideration. The court went on to state, at paragraph 22, as
follows:
I emphasize that underlying all these
factors is the notion that the purpose of the participatory rights contained
within the duty of procedural fairness is to ensure that administrative
decisions are made using a fair and open procedure, appropriate to the
decision being made and its statutory, institutional, and social context,
with an opportunity for those affected by the decision to put forward their
views and evidence fully and have them considered by the decision-maker.
[12] Baker was decided in 1999. Last
year, the statements in that case relating to the duty of fairness were
confirmed by the Supreme Court of Canada in Congregation des te moins de
Jehovah de St. Jerome-Lafontaine v. Lafontaine (Minicipalite), [2004] 2
S.C.R. 650, where Chief Justice McLauchlan stated, at paragraph 5, that the
content of the duty of fairness on a public body varies according to five
factors:
(1) the nature of the decision and the
decision-making process employed by the public organization;
(2) the nature of the statutory scheme and
the precise statutory provisions pursuant to which the public body operates;
(3) the importance of the decision to the
individuals affected;
(4) the legitimate expectations of the
party challenging the decision; and
(5) the nature of the deference accorded
to the body.
[13] In Baker, as well, the Supreme Court
of Canada discussed the narrower issue of when an oral hearing must be held
(at paragraph 33):
However, it cannot be said that an oral
hearing is always necessary to ensure a fair hearing and consideration of
the issues involved. The flexible nature of the duty of fairness recognizes
that meaningful participation can occur in different ways in different
situations. The Federal Court has held that procedural fairness does not
require an oral hearing in these circumstances . . .
[14] Finally, a review of the relevant
case law indicates that a decision on whether to hold a public hearing is
often influenced by consideration of expense, delay and inconvenience. In
fact, the Supreme Court of Canada made the following observation in 1979,
which was approved as a statement of principle earlier this year in a
Newfoundland decision (Johnson v. The Board of Commissioners of Public
Utilities), [2005] NLTD 53:
. . . Fairness, however, does not
necessarily require plurality of hearings or representations and
counter-representations. If there were too much elaboration of procedural
safeguards, nothing could be done simply and quickly and cheaply.
Administrative or executive efficiency and economy should not be too readily
sacrificed . . .
[10] The
Commission has fully considered the request of PEI
Power and is of the view that an oral hearing
is not necessary to ensure a fair hearing and consideration of the issues
involved. Both Maritime Electric and PEI Power have been given an opportunity
to submit material related to the application. The Commission believes that
procedural fairness has occurred in these proceedings through the public
noticing and commenting process and through public access to all of the
documentary evidence submitted by the parties.
4. Discussion & Findings
[11] The evidence
discloses that, at present, energy generated from wind turbines is generally
more costly than conventional sources such as fossil fuel or nuclear power.
However, current forecasts suggest that this may change as fossil fuel
prices continue to increase.
[12] While wind technology
constitutes a significant investment in capital, fuel costs are virtually
non-existent and operating and maintenance costs appear relatively
predictable and manageable. The major downside to wind energy lies in the
variability and availability of wind. However, according to documents on
file, Prince Edward Island's wind regime is among the best in Canada.
[13] In its submissions to the
Commission, Maritime Electric submits that wind energy is the most viable
renewable energy source in Prince Edward Island. According to the Company,
alternative sources such as solar, hydro and organic biomass are either more
expensive or not available.
[14] The Agreement
before the Commission is for 20 years and, if approved by the Commission,
commences, in the case of the 30 MW East Point wind farm, on January 1, 2007
and, in the case of nine MW Norway wind farm, on June 1, 2007. The energy
price in the Agreement is $0.0775 per kWh with $0.02 of this price subject
to an annual CPI index adjustment beginning in April, 2008 using December,
2006 as the base index value. Presently, the price is the same as that
established by the Minimum Purchase Price Regulations under the
Renewable
Energy Act.
[15] Under the Agreement,
Maritime Electric has the right of termination if the price set by the
Agreement is changed by regulation or by operation of law such that the new
price exceeds the price established in the Agreement. The Agreement price
includes any value associated with planning capacity credits that may
eventually be assigned to both wind farm projects. Maritime Electric
anticipates planning capacity credits of 15 MW assigned to these projects.
[16] The 39 MW of renewable
energy covered by the Agreement along with the existing 13 MW at North Cape
will, based on current load forecasts, represent 15% of the 2010 requirement
of 55 MW. According to the Company, entering the Agreement some four years
prior to 2010 will allow the Company time to integrate the characteristics
of wind power into the Company's current energy supply portfolio.
[17] In its submissions to the
Commission, PEI Power states that it has submitted various proposals to the
Government of PEI and to Maritime Electric for the development of wind
projects on P.E.I. PEI Power submits, as well, that it has entered into land
agreements with landowners in Spring Valley, Irishtown and Kensington areas
of P.E.I. for the purpose of developing wind projects.
[18] PEI Power also
submits that:
-
as a crown
corporation, the PEI Energy Corporation is using taxpayer-funded
resources to compete against private sector companies which, in PEI
Power's view, is not the Energy Corporation's role;
[19] A number of
issues raised by PEI Power, including its challenge of the jurisdiction of
the PEI Energy Corporation to acquire power for resale, have been rendered
moot by virtue of recent amendments to the
Renewable Energy Act. Other
non-cost related issues raised by PEI Power are, in the Commission's view,
either beyond our jurisdiction or more properly before the courts. The
Commission does, however, understand PEI Power's frustration in being
effectively shut out of an opportunity to participate in the RPS
requirements of the
Renewable Energy Act.
[20] The Commission's
broad responsibility in this matter is to ensure that Maritime Electric
meets its legislative obligations at the lowest cost consistent with a
public utility's duty to serve. These obligations include the requirement to
provide reasonably safe and adequate service and facilities for services as
changing conditions require and to satisfy the Commission that expenditures
associated with the
Renewable Energy Act are reasonably and prudently
incurred. More specifically, subsections 3(a) and 24(2) of the
Electric Power Act read as follows:
3.
Every public utility shall
(a) furnish at all times such reasonably safe and adequate service and
facilities for services as changing conditions require.
24
(2) The Commission shall allow a public utility to recover, in addition
to the return the public utility is entitled to earn annually under
subsection (1), any expenditures that the Commission is satisfied were
reasonably and prudently incurred by the public utility for the purposes
of complying with requirements of the
Renewable Energy Act.
[21] Maritime
Electric's submissions are that the proposed WPPA satisfy's the utility's
legislative obligations. PEI Power suggests that the WPPA does not.
[22] In response to PEI Power's
submissions, Maritime Electric submits that a formal, competitive process
for renewable energy would not have resulted in any cost savings to the
consumer as the
Minimum Purchase Price Regulations establishes the minimum
price at $0.0775 per kWh regardless of the supplier. In the case of line
losses, Maritime Electric submitted a summary load flow analysis that
indicates that there is only a marginal difference in transmission losses at
either the East Point or Spring Valley locations. According to the Company,
losses on the new lines to connect the wind farms to the transmission system
would be offset by reduced losses due to the unloading of portions of the
existing transmission system in those areas.
[23] In the case of
the costs of the transmission facilities necessary to connect a wind project
to the utility's transmission system, PEI Power submits that those costs
should be borne by the wind developer and not by Maritime Electric and its
ratepayers. PEI Power further submits that this is the industry norm and
that it is prepared to pay these costs in exchange for the $0.0775 per kWh
covered under the
Minimum Purchase Price Regulations. According to PEI
Power:
PEI Power is stating here, in no uncertain terms, that it is prepared to
absorb, within its own capital costs, the projected costs of
transmission line upgrades to its proposed wind farm, all within the
legislated current energy price of 0.0775 cents per Kwh. Not one cent of
such costs would be passed on to the ratepayers and MECL would remain
the legal owner of such upgrades. In addition, PEI Power is prepared to
commit contractually to meeting 100% of MECL' s legislated requirement
of 15% Renewable Energy by 2010 and PEI Power is prepared to post a
substantial performance bond upon execution of a PPA with MECL.
[Written submission dated August 9, 2006, pp.1-2]
[24] In the
Commission's view, there is a distinction to be drawn between transmission
upgrade costs associated with wind generators whose primary function is to
provide electric energy to the interconnecting utility's customers and wind
generators whose primary function is to provide energy, via a utility's
transmission system, to others. In the latter case, Maritime Electric and
its customers provide a conduit to the so-called merchant generator and
should be fully compensated for all capital and operating costs associated
with both the interconnection to, and the transmission of, the merchant
generator's energy. In the former case, the proposed WPPA is, in many ways,
analogous to Maritime Electric contracting with any supplier for energy
purchases or, for that matter, constructing the facility itself. In either
of these situations, Maritime Electric either could or would pay for
transmission upgrades.
[25] The Commission
notes that, while publicly available information supports PEI Power's
contention that interconnection costs associated with wind generators are,
in some cases, borne by the wind generator wishing to connect to the
utility's transmission system, it is not the case that such costs are
universally borne by the wind generator, particularly in situations where
utilities are either contracting for wind energy to meet public service
obligations or building facilities for that purpose. In fact, the opposite
appears to be the case.
[26] Publicly
available information supports Maritime Electric's position that
transmission costs associated with wind facilities that are developed for
the benefit of the utility's customers should be borne by the customers. The
Commission notes, as well, that transmission upgrades associated with wind
projects should improve overall system reliability and stability and,
therefore, provide benefits to the overall system.
In cases where Maritime Electric's customers receive direct benefits from
the interconnection, it is, in the Commission's view, appropriate that
Maritime Electric's customers pay for such benefits.
[27] Having fully
considered the application, the submissions of both Maritime Electric and
PEI Power and the applicable law, the Commission finds and concludes that:
5. Disposition
[28]
An order approving the application and the inclusion of appropriate WPPA costs
in the Energy Cost Adjustment Mechanism will therefore issue.
________________
1.
See http://www.gov.pe.ca.photos/original.ee_frame_rep_e.pdf
2. op cit, p.1
3.
See
https://irac.pe.ca/Orders/Petroleum/2005/PC05-01.htm
Order
UPON
receiving and considering an application by Maritime Electric
Company, Limited (the "Company") for approval of a 39 MW Wind Power
Purchase Agreement;
NOW
THEREFORE , for the
reasons given in the annexed Reasons for Order;
IT IS ORDERED THAT
1.
the application is approved;
and
2. costs
applicable to energy purchased via the Wind Power Purchase Agreement may be
recovered through the operation of the Energy Cost Adjustment Mechanism.
DATED
at
Charlottetown, Prince
Edward Island, this 22nd day of August, 2006.
BY THE COMMISSION:
Maurice Rodgerson, Chair
Weston Rose, Commissioner
James Carragher , Commissioner
Anne Petley, Commissioner
Notice:
Section 12 of the
Island Regulatory and Appeals Commission Act
reads as follows:
12. The Commission
may, in its absolute discretion, review, rescind or vary any order or decision made by it
or rehear any application before deciding it.
Parties to this proceeding seeking a review of the
Commission's decision or order in this matter may do so by filing with the Commission, at
the earliest date, a written Request for Review,
which clearly states the reasons for the review and the nature of the relief sought.
Sections 13.(1) and 13(2) of the Act
provide as follows:
13.(1) An appeal lies
from a decision or order of the Commission to the Appeal Division of the Supreme Court
upon a question of law or jurisdiction.
(2) The appeal shall be
made by filing a notice of appeal in the Supreme Court within twenty days after the
decision or order appealed from and the Civil Procedure Rules respecting appeals apply
with the necessary changes.
|