![](../../../images/iraclogo-n207b.gif)
Docket UE21005
Order UE94-3
IN THE MATTER of an Application
by Maritime Electric Company, Limited for approval to purchase capacity and energy
produced at the Point Lepreau plant and for approval to amortize generation planning
costs.
BEFORE THE COMMISSION
on Friday, the 4th day of March, 1994.
Linda Webber, Chair
John L. Blakney, Vice-Chair
Deborah MacLellan, Commissioner
Reasons for Order
Contents
Appearances & Witnesses
Reasons for Order
Part One
The Application
1.1 Introduction
Part Two
Assessment of the Point Lepreau Purchase
2.1 Introduction
2.2 The Need for Capacity
2.3 Generating Planning Analysis
2.4 Risk Analysis
2.5 The Contract
2.6 Generation Planning Costs
Appearances & Witnesses
1. For Maritime Electric Company, Limited
Counsel:
William G. Lea
Witnesses:
J. A. Lea, Vice-President, Corporate Planning
E. G. Price, Atomic Energy of Canada, Limited
V. G. Snell, Atomic Energy of Canada, Limited
2. For the Minister of Economic Development and Tourism, Government of Prince Edward Island
Counsel:
Shauna Sullivan-Curley
3. For the Prince Edward Island Energy Corporation
John te Raa, Operations Manager
4. For the Town of Summerside
Robert Hughes
5. For the Environmental Coalition of Prince Edward
Island:
Jeremy Stiles
David Daughton
6. For Himself:
Dr. Peter Meincke
7. For The Island Regulatory and Appeals Commission
Counsel:
Thomas A. Matheson
Staff Witness:
D. G. Brown, Consultant
Staff:
Donald G. Sutherland, Director, Utilities Division
George W. Mason, Senior Analyst, Utilities Division
Heather Walker, Recording Secretary
Part One
The Application
1.1 Introduction
This is an application under the
Electric Power and
Telephone Act, R.S.P.E.I. 1988, Cap. E-4 (the "Act") by
Maritime Electric Company, Limited (the "Applicant", "Maritime
Electric", the "Company") seeking approval of The Island Regulatory and
Appeals Commission (the "Commission") for:
1. the purchase of capacity and energy under the terms of a
1994 Point Lepreau Participation Agreement for the period November 1, 1994 to October 1,
2000; and,
2. approval of the amortization of generation planning
costs incurred during the past five years over the same period;
The application was filed on October 21, 1993 and the
Notice of Hearing was published on November 18 and November 22, 1993. A News Release was
issued on January 8, 1994 followed by a further notice on January 11, 1994. Public
hearings followed on January 11, 12 and 13, 1994.
Interventions in this case were filed by the Minister of
Economic Development and Tourism, the Prince Edward Island Energy Corporation, the Town of
Summerside, the Environmental Coalition of Prince Edward Island and Dr. Peter Meincke. Mr.
Dan Brown also appeared as a witness for Commission Staff. As in all proceedings of this
nature, the Commission benefits from the efforts of the interveners. We acknowledge their
contributions.
Part Two
Assessment of the Point Lepreau Purchase
2.1 Introduction
In this proceeding, the assessment of the Point Lepreau
application focused largely on Maritime Electrics need for capacity, the support for
the purchase as a least cost option and an assessment of the risks associated with
generation in general and nuclear power specifically.
2.2 The Need for Capacity
Maritime Electric currently has two electricity contracts
that expire on October 31, 1994. The first is a 5 megawatt (MW) contract for capacity and
energy originating from Hydro Quebec and the second is a 20 MW entitlement in the Point
Lepreau plant. The contract which is the subject of this application is largely an
extension of the latter contract with the entitlement increased to 25 MW and a number of
other modifications. Since the Company is effectively applying for replacement capacity,
the need for new capacity was not raised as a major issue in this hearing.
Some discussion took place about the size of the purchase
and specifically whether a larger or smaller purchase would be optimal. Since the Company
was anticipating a need for additional capacity as early as 1995, a larger purchase might
be justified. On the other hand, the Town of Summerside currently has an application
before the Commission which, if approved, might reduce the Companys requirement for
firm capacity. Opportunities for non-utility generation or an increase in interruptible
capacity are also possible which might offset the anticipated growth in capacity
requirements. Finally, according to Company witness Mr. Lea, the operating reserve
requirements of Maritime Electric place a practical constraint on the amount of capacity
that can be purchased from one plant. On balance, the Commission is satisfied that the
Company has demonstrated that the size of the purchase is reasonable.
2.3 Generation Planning Analysis
Maritime Electrics long term planning was last
reviewed during the Advance Plan hearing in 1992/93. At that time, the Company evaluated a
number of generating alternatives and its preferred option appeared to be an equity
interest in the Point Aconi coal plant in Nova Scotia. When, according to the Company, it
appeared that they could not finalize an agreement without significant delays, the Company
reevaluated the options available. In the interim, the Companys concerns with
respect to the need for retubing at the Point Lepreau plant over the next few years were
alleviated by the results of trials with the Spacer Location and Repositioning (SLAR)
program. The Point Lepreau option was therefore added and a number of other options
dropped for the purposes of the 1993 generation planning analysis.
The major options reviewed by the Company in support of
this application were:
1. Participation in the Belledune coal plant in New
Brunswick;
2. Entitlement in the Point Lepreau plant in New Brunswick;
3. Hydro Quebec contract;
4. Construction of a medium speed diesel plant;
5. Construction of a low speed diesel plant; and
6. Construction of gas turbine/heat recovery steam
generator.
After a preliminary screening, in which the Company
eliminated the higher cost options and identified Point Lepreau as the most likely least
cost option, three scenarios were evaluated for lowest long-term cost:
1. Combined participation in Belledune and Point Lepreau;
2. Participation in Point Lepreau, only; and,
3. Hydro Quebec contract.
Based on this analysis and a sensitivity analysis of the
major economic assumptions, the Company continued to identify Point Lepreau as the least
cost option.
The results of the economic analysis were summarized by
Commission Staff witness, Mr. Brown, as follows:
In summary, my conclusion is that subject to a review of
the risks associated with the different options, the Lepreau purchase for the period under
consideration, 1994 through 2000, is the best option available to MECL and the analysis
supporting this choice as well as the assumptions employed in the analysis are
satisfactory.
(Exhibit I-2, Pg. 3)
Considerable discussion of the various risks took place at
the hearing as is summarized in the following sections.
2.4 Risk Analysis
For the purposes of this analysis, risks are broadly
classified into:
1. Technical Risks associated with plant performance;
2. Economic Risks associated with power costs; and,
3. Other Risks associated with potential liability, etc.
Clearly, these risks are interrelated and the arbitrary
classification is intended only for ease of discussion.
2.4.1 Technical Risks
The major technical risks discussed included issues related
to:
1. The need for retubing during the contract period;
2. Failure of the steam generator; and,
3. Failure of transmission capability to Prince Edward
Island.
Prior to the current application, Maritime Electric had
expressed reservations about continued participation in the Point Lepreau plant because of
the uncertainty about when retubing, a major plant investment, would be required. The
Companys concerns have apparently been satisfied, at least in part, by recent
activities at the plant which were addressed by Company witness Mr. E.G. Price of Atomic
Energy Canada, Limited. Mr. Price described in detail the Spacer Location and
Repositioning (SLAR) program that had undergone trials at Point Lepreau (and other CANDU
plants) and was planned for full implementation in early 1995. In summary, Mr. Price
concluded that he was confident that the SLAR program would proceed as planned to restore
the reactor tubes to design conditions and that, once completed, the risk of retubing
being required during the term of this contract was very low.
The other risks related to the SLAR program are that it
would take much longer than expected or that the capital cost would be much higher than
expected. In terms of duration, Maritime Electrics evidence indicates that the total
cost for power resulting from the participation agreement during the SLAR outage is
expected to be similar to the power cost when the plant is operating. The power cost would
therefore be expected to increase significantly only if there was a major change in power
markets in the short term or if the program took considerably longer than anticipated.
Both of these risks appear to be addressed satisfactorily. The capital cost risk also
appears to be limited since the cost of the SLAR program makes up a small, though not
insignificant, part of the overall plant cost.
Mr. Price also addressed the potential problems with steam
generators which are another area of concern in CANDU plants. According to Mr. Price, the
steam generators at Point Lepreau are in good condition and, as long as the regular
maintenance now performed at the plant continues, should not result in any significant
risk to planned plant performance.
The other major components of the plant, according to Mr.
Price, are similar to those in other plants and should not present any unusual risk which
is not common to conventional generating plants.
Another risk common to all generation purchases from
off-Island sources is the risk of a failure in the capability to transmit the energy to
Prince Edward Island. In general terms, this has been of concern for some time and has
been addressed, in part, by improvements to the transmission system in New Brunswick and
to the interconnection that were completed in recent years. The risk, however, remains
that Maritime Electric will have to pay for its entitlement when, due to system failure,
it cannot receive the electricity. This risk is reduced, though not eliminated, by the
Article XV of the contract by which NB Power agrees to purchase undeliverable power at
their avoided cost. In the view of the Commission, the remaining risk is acceptable given
the economic benefits projected to result from the contract.
In assessing the risks associated with nuclear plants, it
is difficult to avoid consideration of a major plant catastrophe. Company witness Mr.
Snell of AECL addressed the problem with the following principle points:
1. The major reactor failure to date at Chernobyl resulted
from a design that is much different and from faults that are much less likely to occur in
a CANDU designed unit;
2. The major failure in North America at the Three Mile
Island plant was fully contained and did not have significant impacts (other than economic
ones) beyond the plant site; and,
3. The overall risk of a major failure is very small and
has been quantified in the order of one every ten thousand reactor-years.
While none of these points do or can eliminate the
possibility that the plant will be shut down during the contract period, they do satisfy
us that the risk is low. The plant is already in operation and our physical exposure in
this province is similar whether or not we are receiving power from the plant.
Further on the issue of risk, the Commission recognizes
that there is a difference between the issues related to participating in an existing
plant versus those related to participating in the construction of a new facility. Were we
looking at the latter case, our view of the risks discussed above might be different.
2.4.2 Economic Risks
The major economic risks discussed included:
1. Fuel supply and price risk;
2. Financial risks related to inflation, exchange rate
fluctuations and interest rates; and,
3. Plant decommissioning and fuel disposal risks;
Fuel risks were addressed principally by the AECL witnesses
who assessed them as very low. With respect to supply, Canada was stated to have ample
supply from its existing mines as well as significant uranium reserves for potential
future development. In terms of price, AECL witness Mr. Price stated that the fuel price
makes up a relatively small portion of the total power cost and that even a major change
in fuel bundle prices should have a relatively modest impact on overall power costs.
Financial risks were assessed by Company witness Mr. Lea
and Commission Staff witness Mr. Brown. Their testimony essentially concluded that many of
the risks are common to all of the optionsto varying degreesand that those risks which might be greater for Point Lepreau
participation are acceptable when considering the projected benefits of this option over
the contract period.
The plant decommissioning and fuel disposal risks were
presented as issues related primarily to continued participation beyond the term of the
proposed contract. On this basis, it would appear that the major risks are related to New
Brunswick Power determining that its decommissioning and irradiated fuel management
funding is insufficient and has to be increased significantly. The current estimates
appear to indicate that funding is sufficient; however, the Commission notes that
according to the Companys witnesses, acceptable, long-term solutions to these
problems have not been reached and the issues may become increasingly important if a
contract extension is considered.
2.4.3 Other Risks
The other major risks discussed related to regulatory risk
and a current court challenge to the Nuclear Liability Act. Mr. Snell of
AECL addressed regulatory risk from the perspective of the Atomic Energy Control Board
imposing stricter or new requirements on the operation of the plant which would impact on
the cost or even viability of operating the plant. In his view, as long as NB Power
continued to operate the plant in a reasonable manner, regulatory risk was very low. The
other participants did not challenge his opinion.
Another concern is related to the current challenge of the
Nuclear
Liability Act which currently limits the liability of the operator of a nuclear
plant from third party losses caused by a nuclear accident. On review of the evidence
before us, it appears that this issue is not likely to be resolved for many years and will
be of greater concern when the contract extension option is considered.
2.4.4 Positions of Interveners
The only party opposing the application was the
Environmental Coalition of Prince Edward Island (ECOPEI). They are opposed to nuclear
power on economic and environmental grounds. Unfortunately, their participation was
limited largely to issues which were insufficiently supported by fact and which were, in
our view, addressed satisfactorily by the Company and its witnesses.
ECOPEI did, in our view, raise a valid concern about the
process that led up to this application. At the Advance Plan hearing a year earlier, Point
Lepreau was not even viewed as a major option, but rather as a possible source of
"bridging" capacity. The Companys preferred option was participation in
the Point Aconi plant in Nova Scotia and ECOPEI was prepared to challenge that
participation, which they also opposed. Instead, less than a year later, the Company came
forward with a totally different option.
The Commission is concerned about whether this is an
indication of initial inadequate planning on behalf of the Company followed by a lack of
communications with other interested parties. In terms of planning, some discussion took
place at the hearing with respect to whether the Companys planning staff was
adequate. In terms of communications, it is possible that there is a need for keeping
parties up to date on developments when it is known that they have an interest. We expect
the Company to review these matters and ensure that they are appropriately addressed in
the future.
Mr. Peter Meincke intervened on his own behalf to discuss
what he felt was a broader responsibility of the Company and others for making sound
energy choices in the future. He believes that the Commission has no choice but to approve
this application; however, he also feels that the province has lost its leadership role in
small and more environmentally acceptable alternatives. The Commission believes that Mr.
Meincke raised issues which may well be worth pursuing and we look forward to his
participation at future hearings.
The Prince Edward Island Energy Corporations major
interest in this application appeared to be to ensure that there was some capacity
"set aside" to allow for their plans as a Non-Utility Generator. We understand
that the Energy Corporations objective has, at least in part, been addressed by the
expected need for additional capacity in the near term.
The Minister of Economic Development and Tourism supported
the proposed contract as being in the best interests of electricity consumers in the
province.
1. The proposed 1994 Point Lepreau Participation Agreement is approved;
2. The Company shall make application to the Commission for approval of any
proposed amendments to the Agreement, including any proposal to exercise any option, in
sufficient time for such changes to be reviewed by the Commission and by interested
parties;
3. The Company shall update the Commission annually, on matters related to the
participation in Point Lepreau and the possible exercise of the option;
2.5 The Contract
2.5.1 Introduction
The 1994 Point Lepreau Participation Agreement is, in most
ways, similar to the agreement approved by the Commission in 1990. The major differences
relate to the SLAR outage, discussed above, and the option to extend the agreement for the
life of the plant. The Company also proposes to negotiate changes to address possible
future changes in the ownership of the plant.
2.5.2 The Option
The proposed contract includes an option for Maritime
Electric to extend its participation to the useful life of the plant at any time during
the contract period. In exchange for this option, Maritime Electric effectively pays
approximately $1 million per year until such time as the option is exercised (or the
contract terminates). This option is argued to give Maritime Electric significant benefits
as it provides an opportunity for long term power at reasonable cost at the same time that
it allows them to let their obligations lapse at the end of the contract if further
participation does not appear to be attractive. While no participant was willing to assign
a value to the benefits of the optionits assessment being largely judgmentalthere was no strong
opposition to it. The Commission is satisfied that this option is reasonable.
The accounting treatment of the option was not discussed at
the hearing. At issue might be whether the benefits of the optioneither participation in
low cost generation or avoidance of high cost power beyond 2000should be paid by rate
payers during the contract period or beyond. Our understanding is that the Company intends
to expense the cost of the option as incurred. Due to the uncertainty of future benefits
and the practical problems with deferral, we accept this approach.
In terms of a decision to exercise the option, Commission
Staff witness, Mr. Brown, made the following comments:
In my opinion the option should be retained and every
effort made to determine NBPCs intent with respect to pressure tube replacement now
contemplated for the year 2008. Its possible that the utility in New Brunswick may
decide to retire the unit rather than go ahead with pressure tube replacement in 2008.
Although, at least in my opinion, this is unlikely since there are those who believe that
the pressure tube and steam generator tube replacement can result in an overall life of 60
years for this unit. Thus it would seem reasonable to expect the utility in New Brunswick
to opt for life extension of this unit. However, at this point this is not at all certain
and it would be prudent for MECL to wait until after the SLAR program has been completed
and further analysis has been done on the condition of the pressure tubes and steam
generator tubes has been completed. ...
(Exhibit I-2, Pg. 6)
The Commission tends to agree that the options
purpose is to avoid risk and that it should not be exercised, if it is exercised at all,
until the risks of future participation can be better evaluated. The Company has also
committed to make further application before any proposed exercise of the option is
executed and we expect it to do so.
2.5.3 Privatization Clause
Commission staff witness, Mr. Dan Brown, raised the issue
of the potential impact on the contract if NB Power were to be privatized over the
contract period. While it is not known whether any such plan exists, Nova Scotia Power has
recently been privatized and plans have been announced to privatize part of Newfoundland
and Labrador Hydro. In such an environment, the issue of privatization merits
consideration.
Since the contract only allows for capital related costs
associated with debt, there is no provision for possible privatization of NB Power.
Maritime Electric has requested that the Commission proceed to reach a decision on the
application as presented and that approval be granted on condition that the approval is
subject to further approval of amendments related to privatization.
Based on the evidence presented we do not believe that the
specific condition requested by the Company is necessary. It appears to us that the
privatization clause is largely in the interest of fairness to NB Power as it is likely to
increase rather than decrease the cost of the contract to Maritime Electric. Therefore,
its omission should not necessarily cause us to withhold our approval. We view this like
any other amendment which we would expect the Company to bring forward for approval before
executing.
2.6 Generation Planning Costs
The past practice of the Company has been to accumulate
costs associated with generation planning in a deferred account and then to either
capitalize them with the new investment or amortize them over the life of the resulting
contract. In this application, the Company proposes to amortize approximately $1.4 million
in costs incurred over the last five years over the period November 1, 1994 to October 31,
2000, the term of the contract. Company witness, Mr. J. A. Lea responded, with respect to
questioning related to IRACStaff 3.1 (Exhibit M-3), that the Company would have no
particular objection to amortizing the costs over a modified period, for example, the
period January 1, 1994 to December 31, 2000. In the view of the Commission, this appears
to be more consistent with recent practice and also achieves some stability of costs,
especially in 1994.
4. The Company shall amortize generation planning costs that have led up to this
application on a straight line basis over the revised period January 1, 1994 to December
31, 2000;
5. This Order does not apply to proposed amendments to the agreement related to
possible changes in ownership structure for the plant; and
6. The proposed amendments referred to in paragraph 5 herein will be considered
by the Commission at a later date.
DATED at
Charlottetown, Prince Edward Island, this 4th day of March, 1994.
BY THE COMMISSION:
Linda Webber, Chair
John L. Blakney, Vice-Chair
Deborah MacLellan, Commissioner