Docket UE20708
Order UE94-4
IN THE MATTER
of an application
by Maritime Electric Company, Limited for approval of the 1994 capital budget.
BEFORE THE COMMISSION
on Friday, the 4th day of March, 1994.
Linda Webber, Chair
John L. Blakney, Vice-Chair
Deborah MacLellan, Commissioner
Order
Contents
Appearances & Witnesses
Reasons for Order
1 Introduction
2 The Application
2.1 Summary
2.2 Demand Side Management
2.3 General Expenditures
2.4 Production
2.5 City Distribution
2.6 Rural Distribution
2.7 Transmission
2.8 Capitalized General Expenses
3 Other Matters
3.1 Supplementary Capital Items1992
3.2 Supplementary Capital Items1993
3.3 Supplementary Capital ItemsGeneral
3.4 Disposition
Order
Appearances & Witnesses
1. For Maritime Electric Company, Limited
Counsel:
William G. Lea
Witnesses:
Philip Hughes, Vice-President, Finance and Administration and
Chief Financial Officer
P. H. Newcombe, Vice-President, Production and Energy Supply
J. A. Lea, Vice-President, Corporate Planning
J. Landrigan, Director, Customer Service
2. For the Minister of Economic Development and
Tourism, Government of Prince Edward Island
Counsel:
Shauna Sullivan-Curley
3. For the Prince Edward Island Energy Corporation
John te Raa, Operations Manager
4. For the Town of Summerside
Robert Hughes
5. For The Island Regulatory and Appeals Commission
Counsel:
Thomas A. Matheson
Staff:
Donald G. Sutherland, Director, Utilities Division
George W. Mason, Senior Analyst, Utilities Division
Heather Walker, Recording Secretary
Reasons for Order
1 Introduction
This is an application by Maritime Electric Company, Limited
("Maritime Electric", the "Company") for approval of the Company's
1994 capital budget. The application was filed with the Commission on October 25, 1993
and, except for those parts related to demand side management and the Dalhousie plant
conversion, was heard in public before the Commission on December 7, 8 and 9, 1993, after
due public notice. Interventions in this case were filed by the Town of Summerside, the
Minister of Economic Development and Tourism (the "Minister") and the Prince
Edward Island Energy Corporation (the "Energy Corporation").
The sections on demand side management and the Dalhousie
plant conversion were to be heard at a later date and will be the subject of a subsequent
order or orders.
2 The Application
2.1 Summary
Table 1 shows a summary of the major account items submitted
to the Commission for approval.
Table 1
Summary of 1994 Capital Budget
Major Account
|
Amount |
Demand Side Management
|
$ 506,000 |
General
|
752,000 |
Production-Regular
|
4,486,000 |
Production-Dalhousie Conversion
|
20,300,000 |
City Distribution
|
1,504,000 |
Rural Distribution
|
4,714,000 |
Transmission
|
170,000 |
|
$32,432,000 |
Capitalized General Expenses
|
2,160,700 |
Total
|
$34,592,700 |
|
|
Contributions
|
|
Demand Side Management
|
6,000 |
City Distribution
|
40,000 |
Rural Distribution
|
335,000 |
|
381,000 |
Net Total
|
$ 34,211,700 |
2.2 Demand Side Management
In Order UE93-6, the 1993 capital budget order, the
Commission determined that the whole demand side management strategy of the Company was in
need of review. The Company was therefore ordered to file a comprehensive report on demand
side management as part of its 1994 capital budget. The Company notified the Commission
that it did not expect to have the report completed until January 1994 and proposed to
continue with existing programs until the review was completed.
While the Commission heard the evidence on Demand Side
Management prior to issuing this order, further time is needed to consider the proposals
made by the Company. In the meantime, the Companys request to continue with ongoing
programs will be approved.
1. The Companys proposal to continue with ongoing
programs until further direction is given on Demand Side Management is approved.
2.3 General Expenditures
General Capital Items proposed for 1994 are shown in Table
2.
Table 2
1994 General Budget
Item |
Program |
Amount |
G-1 |
Office Equipment and Furniture |
111,000 |
G-2 |
Management Information Systems |
531,000 |
G-3 |
Mail Inserter |
110,000 |
|
Total |
$ 752,000 |
In Order UE93-6, the Commission focused on the Management
Information Systems (MIS) budget and, in particular, the lack of planning in this area
apparent at that time. Approval of most of the budget was withheld pending approval of an
MIS plan. The plan was subsequently filed in mid-1993 and the Company's proposed
acquisitions for 1993 were approved in Order UE93-8.
The current application led to some difficulties in
comparing the company's proposed expenditures for 1994 with those proposed in the MIS
plan. While the MIS plan is not expected to remain static, the Commission is interested in
comparing expenditures each year with the Companys long term plan. Such monitoring
would include significant changes in equipment and projects that might be planned from one
filing to the next. We believe that this can be achieved with some straight-forward
modifications to the Company's MIS updates and capital budget filings.
Effective for 1994, the Company also proposes to change its
accounting policy from expensing application software development costs to capitalizing
the costs and depreciating them over 5 years. The change was proposed to achieve a better
matching between the cost of software and its use. Changing the policy would also reduce
the revenue requirement in the short-term at the price of a higher revenue requirement in
the long term as financing costs are added, an impact typical of any expenditure that is
capitalized. Since application software is generally considered to have a useful life
beyond one year, the Companys general proposal appears reasonable. At issue is
whether the policy should be phased in to smooth its impact on revenue requirement over
the next 5 years. In this case, we do not consider a phase in to be necessary since the
overall impact appears to be acceptable. The actual depreciation rate will be reviewed at
the next rate case.
With respect to item G-1, the Company indicated that its
estimate for photocopiers was $10,000 higher than now appears to be necessary.
Accordingly, this item will be reduced by $10,000.
Also discussed with respect to these accounts was the
Company's policy for leasing. The discussion was initiated, in part, because the Company
is seeking approval for a number of purchasesnamely photocopierswhich have typically been leased in the past. The Company indicated
that it was seeking approval even though the decision had not been made on whether the
assets would be purchased or leased. In principle, we support the Companys analysis
of leasing versus buying assets so long as the objective is to provide the lowest
long-term cost to customers. We therefore consider some flexibility in the approved
capital budget to be reasonable.
In the past, such "acquisitions" have not come to
our attention at allunless the specific operating account was examinedbecause the assets
were leased. In the future, the Company should provide an annual update to the lease
report as part of its capital budget application.
2. The Company shall modify it MIS filings to highlight
changes, if any, proposed in its long-term plan and to provide a comparison of budgeted
expenditures proposed for the upcoming year with the long-term plan.
3. The Companys proposal to capitalize application
software development costs in the future is approved.
4. The Company shall provide an annual update of assets under
lease that have a cost value of $10,000 or more.
5. General expenditures are approved in the reduced amount of
$742,000.
2.4 Production
Production Expenditures proposed for 1994 are shown in Table
3.
Table 3
1993 Production Budget
Item |
Program |
Amount |
P-1 |
Misc. Mechanical Equipment |
5,000 |
P-2 |
Misc. Electrical Equipment |
3,000 |
P-3 |
Engineering & Test Equipment |
0 |
P-4 |
Plant Maintenance Shop Tools |
10,000 |
P-5 |
Dalhousie Capital Additions |
20,300,000 |
P-6 |
Steam Plant Life Extension |
4,064,000 |
P-7 |
Generation Planning Studies |
0 |
P-8 |
Communications System Development |
27,000 |
P-9 |
Supervisory System Development |
0 |
P-10 |
Transmission Substation Additions |
158,000 |
P-11 |
Charlottetown Plant Projects |
50,000 |
P-12 |
Borden Plant Projects |
66,000 |
P-13 |
Submarine Cable Projects |
103,000 |
|
Total |
$ 24,786,000 |
Expenditures related to P-5, Dalhousie Capital Additions, is
the subject of a future hearing.
The Company is in the fifth year of what is now a six year
(originally five-year) steam plant-life extension project. The current forecast continues
to indicate that the overall project remains approximately within the original budget
except for the additional expenditures needed to extend the life of Unit No. 5 which was
originally scheduled for retirement.
The majority of the work left on the plant life extension
project is related to the older boilers or what is referred to as the "old end of the
plant". As it is completing the life extension, the Company is also evaluating the
opportunity for extended shutdown or "lay-up". Considerable discussion took
place at the hearing on what appeared to be a plan to invest $5 million dollars in assets
which would then be "laid up" because it may not be necessary to keep them on
standby for the next few years. The Companys response was that the old end of the
plant had continued value as planning reserve, but that with surplus capacity in the
region, the Company may not need operating reserve available on short notice over the next
few years. In the view of the Commission, the final phase of the project is still,
therefore, supportable.
In Order E91-4 of the Public Utilities Commission, the
Company was directed to file:
a detailed workplan for the Commissions review that
will see improvements in the appearance of the Charlottetown generating station commenced
this year and completed by the end of 1994.
(PUC Order E91-4)
The Company filed an appeal of that section of the order at
the time and effectively halted further improvements to plant aesthetics. At the
commencement of the current hearing, the Company informed the Commission that the appeal
had been dropped and that it would be filing in early 1994 to extend the deadline in the
original order. Since a number of years have passed in the interim, the Commission
believes that the work done on the plant and the Companys future plans should be
reviewed as a logical next step in this project.
With respect to P-13, the Company indicated in response to
interrogatory IRACStaff 3.5 (Exhibit M-4) that it is not now seeking approval as it is
uncertain who will be paying for this project. The Government of Prince Edward Island owns
these cables and certain capital expenditures may be recoverable from the Cable
Replacement Fund. The Commission will therefore defer this item until the Company comes
forward with a further proposal.
6. The Company shall file, by September 30, 1994, a summary
of work done to improve the appearance of the Charlottetown plant as well as its proposal
for future improvements. >
7. Production expenditures in the reduced amount of
$4,383,000 are approved.>
2.5 City Distribution
Proposed 1994 City Distribution expenditures are shown in
Table 4.
Table 4
1994 City Distribution Budget
Item |
Program |
Amount |
C-1 |
Replacements due to Storm,
Collision, Fire and Deterioration |
10,000 |
C-2 |
Rebuilds Due to Street Alterations |
5,000 |
C-3 |
City Distribution Transformers |
164,000 |
C-4 |
New City Service Lines |
39,000 |
C-5 |
Upgrading City Service Line |
28,000 |
C-6 |
Street and Yard Lighting |
31,000 |
C-7 |
Distribution Line Extensions |
20,000 |
C-8 |
Distribution Line Rebuilds |
90,000 |
C-9 |
System Meters |
390,000 |
C-10 |
Line Tools |
42,000 |
C-11 |
Engineering & Test Equipment |
22,000 |
C-12 |
Transportation Equipment |
597,000 |
C-13 |
Rebuilds Due to Joint Use |
5,000 |
C-14 |
Transformer Shop Equipment |
4,000 |
C-15 |
Meter Shop Equipment |
17,000 |
C-16 |
Job Order Transfers |
40,000 |
|
Total |
$ 1,504,000 |
|
|
|
|
Less Contributions: |
|
C-16 |
Job Order Transfers (100%) |
40,000 |
|
|
|
|
Net Total |
$ 1,464,000 |
At the 1993 Capital Budget hearing, discussions focused on
the significant reductions in many City accounts, with some less than half the 1992
levels. Based on expenditures to date in 1993, it is clear that these reductions were not
realized and the company's expenditures approached historical levels. As a result, the
Company changed its forecasting methodology to a five-year weighted average approach and,
for 1993, is forecasting activity at closer to historical levels.
Most of these accounts are either replacement or customer
driven. In the latter case, the Company provides service when it is demanded and spends
either above or below its budget in accordance with customer requirements. Some discussion
took place at the hearing with respect to whether the Company should be seeking further
approvals when, for example, it knows part way through the year that it is likely to be
well over budget. This issue is addressed in the last section of the report.
The Company has also eliminated the budget for contributions
based on the new contribution policy it is proposing as part of the revised Prince
Edward Island Electric Utilities General Rules and Regulations. Since these
will not be reviewed until later in 1994, the Company should continue to receive
contributions as per the existing schedule. While this should not affect the capital
expenditures, it will reduce the net amount which the Company has to finance.
8. City Distribution expenditures of $1,504,000 are approved.
2.6 Rural Distribution
Proposed Rural Distribution Expenditures for 1994 are shown
in Table 5.
Table 5
1994 Rural Distribution Budget
Item |
Program |
Amount |
R-1 |
Replacements due to Storm,
Collision & Fire |
75,000 |
R-2 |
Rebuilds Due to Road Alteration |
10,000 |
R-3 |
Rural Distribution Transformers |
750,000 |
R-4 |
New Rural Service Lines |
679,000 |
R-5 |
Upgrading Rural Service Line |
253,000 |
R-6 |
Street and Yard Lighting |
53,000 |
R-7 |
Distribution Line Extensions |
222,000 |
R-8 |
Line Rebuilds & Improvements
(1) |
688,000 |
R-9 |
Line Control Devices |
86,000 |
R-10 |
Rebuilds Due to Joint Use (1) |
400,000 |
R-11 |
Job Order Transfers |
84,000 |
R-12 |
Pole Replacement Program (1) |
1,312,000 |
R-13 |
U/G Replacements - Slemon Park |
77,000 |
R-14 |
Rosebank Stores Upgrade |
25,000 |
|
Total |
$ 4,714,000 |
|
|
|
|
Less Contributions: |
|
R-4 |
Contributions for New Rural
Service Lines |
65,000 |
R-7 |
Contributions for Distribution
Line Extensions |
6,000 |
R-10 |
Rebuilds Due to Joint Use (45%) |
180,000 |
R-11 |
Job Order Transfers (100%) |
84,000 |
|
|
335,000 |
|
|
|
|
Net Total |
$ 4,379,000 |
The Commission continues to monitor accounts R-8: Line
Rebuilds and Improvements and R-12: Pole Replacement Program to ensure that the rural
distribution system is maintained and improved. In recent years, the Companys budget
for these accounts has averaged approximately $2 million and has continued to focus on
high priority lines. Combined with the greater emphasis on joint use construction with
Island Tel, the Companys investment in the rural system appears to be acceptable.
As noted under City Distribution, the budget for
contributions is likely low, and will have the same impact as stated above.
9. Rural Distribution expenditures of $4,714,000 are
approved.
2.7 Transmission
The proposed transmission expenditures for 1994 are shown on
Table 6.
Table 6
1994 Transmission Budget
Item |
Program |
Amount |
T-1 |
Replacements Due to Storm,
Collision, Fire and Deterioration |
$ 10,000 |
T-2 |
Rebuilds Due to Road Construction |
10,000 |
T-3 |
Rebuild Transmission Line T-10 |
150,000 |
|
Total |
$ 170,000 |
Item T-3 was originally budgeted as a 1994 project. The
Company subsequently filed a supplementary budget request for 1993, seeking approval to
initiate the project early. Approval was granted by Order UE93-20 on December 9, 1993 for
both the 1993 and 1994 budgets.
10. Additional Transmission expenditures of $20,000 are
approved.
2.8 Capitalized General Expenses
Capitalized General Expense represents general overheads
associated with capital items to be installed or constructed in 1994 that the Company
proposes to capitalize. While the Company has reorganized its accounts, no major issues
were raised and the budget will be approved.
11. Capitalized General Expenses of $2,160,700 are approved.
3 Other Matters
3.1 Supplementary Capital
Items1992
Supplementary Capital Items typically represent projects for
which the Companys expenditures were greater than budgeted or which were not
anticipated at the time of the initial budget. These items have been reviewed by the
Commission and will be approved as filed.
12. Supplementary Capital Items for 1992 are approved as
filed.
3.2 Supplementary Capital
Items1993
The Company also applied for approval to advance the
construction on Transmission Line T-10 into 1993 and for approval of $396,000 related to a
new administration building at the Dalhousie plant. Approval of the T-10 project was given
in Order UE93-20, dated December 9, 1993.
The discussion of the Dalhousie administration building
focused on whether the building should be considered as part of the overall Dalhousie
project. Subsequent to the hearing, the Company was notified that the Commission was
unwilling to approve the expenditure until a full review of the Dalhousie upgrade was
completed. The hearing is still pending.
3.3 Supplementary Capital
ItemsGeneral
The issue of when the Company should apply for approval of
supplementary capital expenditures has been an issue for a number of years. Reference has
been made in recent hearings to the requirement for advance approval if expenditures are
going to be $50,000 or more over budget on any particular account. After the hearing
Commission Staff reviewed capital budget orders for directions on this issue and has
provided a summary of the same to the Company. The Commission believes that some
clarification is required.
The requirement for prior approval results from s. 6(1) of
the Act and also from the desire to avoid having the Commission disallow an
expenditure after it has already been made. Section 6(1) effectively requires prior
approval to commence any project costing more than $5,000. At issue, therefore, is whether
advance approval is required when the Company knows it is going to exceed the approved
budget for a project. For practical purposes, the Commission has allowed some flexibility
in this area so that the Company does not have to seek approval for every small variation
from the budget. We do believe, however, that a guideline is required in this area along
the lines of the $50,000 limit mentioned above. In our review, an over expenditure of 10%
is material and should be reported subject to reasonable limitations.
13. The Company shall seek further approval from the
Commission when any change in expenditures on any Capital Budget Item is material.
3.4 Disposition
An Order will therefore issue.
IN THE MATTER of an application
by Maritime Electric Company, Limited for approval of the 1994 capital budget.
Order
WHEREAS Maritime
Electric Company, Limited (the "Company"), by application filed with the Island
Regulatory and Appeals Commission (the "Commission") on October 25, 1993,
applied for approval of the Company's 1994 capital budget;
AND WHEREAS the Commission heard the application, excepting those parts related
to demand side management and the Dalhousie plant conversion, at public hearings conducted
in Charlottetown on December 7, 8 and 9, 1993 after due public notice;
AND WHEREAS the Commission has issued its findings in this matter in accordance
with the Reasons for Order issued with this Order;
NOW THEREFORE,
pursuant to the Island Regulatory and Appeals Commission Act and the Electric
Power and Telephone Act;
IT IS ORDERED THAT
1. The Companys proposal to continue with ongoing
programs until further direction is given on Demand Side Management is approved.
2. The Company shall modify it MIS filings to highlight
changes, if any, proposed in its long-term plan and to provide a comparison of budgeted
expenditures proposed for the upcoming year with the long-term plan.
3. The Companys proposal to capitalize application
software development costs in the future is approved.
4. The Company shall provide an annual update of assets
under lease that have a cost value of $10,000 or more.
5. General expenditures are approved in the reduced amount
of $742,000.
6. The Company shall file, by September 30, 1994, a summary
of work done to improve the appearance of the Charlottetown plant as well as its proposal
for future improvements.
7. Production expenditures in the reduced amount of
$4,383,000 are approved.
8. City Distribution expenditures of $1,504,000 are
approved.
9. Rural Distribution expenditures of $4,714,000 are
approved.
10. Additional Transmission expenditures of $20,000 are
approved.
11. Capitalized General Expenses of $2,160,700 are
approved.
12. Supplementary Capital Items for 1992 are approved as
filed.
13. The Company shall seek further approval from the
Commission when any change in expenditures on any Capital Budget Item is material.
DATED at
Charlottetown, Prince Edward Island, this 4th day of March, 1994.
BY THE COMMISSION:
Linda Webber, Chair
John L. Blakney, Vice-Chair
Deborah MacLellan, Commissioner
NOTICE
Section 12 of the Island Regulatory and Appeals
Commission Act reads as follows:
12. The Commission may, in its absolute discretion,
review, rescind or vary any order or decision made by it or rehear any application before
deciding it.
Parties to this proceeding seeking a review of the
Commission's decision or order in this matter may do so by filing with the Commission, at
the earliest date, a written Request for Review, which clearly states the reasons
for the review and the nature of the relief sought.
Sections 13.(1) and 13(2) of the Act provide
as follows:
13.(1) An appeal lies from a decision or order of the
Commission to the Appeal Division of the Supreme Court upon a question of law or
jurisdiction.
(2) The appeal shall be made by filing a notice of appeal
in the Supreme Court within twenty days after the decision or order appealed from and the
Civil Procedure Rules respecting appeals apply with the necessary changes.