Docket UW46301
Order UW94-11
IN THE MATTER of an application by the Cavendish Sewer Utility for interim approval of a
Tariff for sanitary sewer services.
BEFORE THE COMMISSION
on Thursday, the 23rd day of June, 1994.
Linda Webber, Chair
John L. Blakney, Vice-Chair
Deborah MacLellan, Commissioner
Order
Contents
1. Introduction
2. The Applicant
3. Tariff Proposals
4. Findings
5. Disposition
Order
Appearances & Witnesses
1. For the Cavendish Sewer Utility:
Walter Wyand, Chairman
David Ellis, Consultant
2. For Cavendish Sunset Campground:
Bill Hogg
3. For Holiday Haven Campground:
Annet Tol
4. For Ocean View Campground:
Janet Hryckiw
5. For Rainbow Valley:
Earl Davison
6. For Marco Polo Land:
Larry Dumville representing Dr. K.G. Ellis
7. For Chez Yvonne Restaurant:
Paul Larkin
8. For the Island Regulatory and Appeals
Commission
Staff:
Donald G. Sutherland
Director, Utilities Division
Shayne A. Hogan
Research Analyst
Heather Walker
Recording Secretary
Reasons for Order
1. Introduction
This is an application under the Water and Sewerage
Act, R.S.P.E.I. 1988, Cap. W-2, as amended, by the Cavendish Sewer Utility
("applicant" or "utility"). The applicant seeks interim approval of a
Tariff for sanitary sewer services provided to customers served or capable of being served
by the utility's sewage collection and treatment system.
The application in this matter was originally filed with
the Commission on July 14, 1993 and an initial public hearing was held on November 10,
1993. The application was subsequently revised and re-filed on March 30, 1994 and the
hearing reconvened on June 9, 1994 to consider the revisions to the original application.
2. The Applicant
The applicant is a body corporate and a public utility
within the meaning of the Water and Sewerage Act. According to the
applicant, the Cavendish sewage collection and treatment system consists of the following
facilities:
The system consists of approximately 6200 meters of
gravity sewer main, 3600 meters of force main, 600 meters of service laterals, five
pumping stations and the treatment facility. The treatment facility includes a three acre
aerated lagoon and related blower building, two holding lagoons (total area of
approximately six acres) and the outfall line (including a pumping station).
(Exhibit 1, p.2)
The historical development of the system and the areas
serviced are described by the applicant this way:
The project was tendered in five packages. Four of these
were essentially for the collection system, the fifth was for the treatment facility. As
of January 1993, the collection system was essentially complete from an operational
standpoint. The aerated lagoon was operational and accepting effluent on May 15, 1993. The
balance of the work (primarily the four acre holding cell) at the treatment facility [was]
completed in the early summer of 1993.
The properties serviced include the following areas:
- Route 6 from the Cavendish Boardwalk to the Gulf View
Cottages
- Cavendish Maples Lane
- Forest Hills Lane to the Chinney Chin Inn
- Kindred Spirits Lane
- Route 13 from the former school north to Ingleside Lodge
- Lane way servicing five cottages behind Chevy's bar
- MacCoubrey Lane (which provides service to the Marco Polo
Campground
The customer base for the utility is 98 representing
487.12 proportionate sewer units and 32,701 feet of frontage.
(Exhibit 1, pp. 2-3)
The overall capital cost of the system is estimated at
approximately $3,000,000. Grants from federal and provincial governments total some
$2,350,000. The balance of the cost is to be borne by the utility and recovered from
customers. By Order UW93-11 dated June 30, 1993, the Commission authorized a non-recurring
capital contribution charge of $4.00 per lineal foot based on a minimum frontage of 100
lineal feet to each property fronting on a utility sanitary sewerage main. The applicant
estimates that the capital recovery from this charge will amount to some $134,000 with the
balanceapproximately $480,000to be financed by the utility and recovered
through annual user rates.
3. Tariff Proposals
In addition to the non-recurring capital contribution
charge authorized under Order UW93-11, the applicant originally proposed the following
tariff items:
- an annual frontage rate of $1.00 per foot - to a maximum of
$500 - with a 100 foot exemption for each proportionate unit charged the customer;
- an annual customer charge of $102.04 for each customer;
- an annual demand charge of $109.43 per proportionate unit;
and
- a flow charge of $1.17 per cubic meter.
The rates were based on the following expense estimates and
allocation of costs:
Table 1
Cavendish Sewer Utility
Original Allocation of Expenses and Rate
Proposals
The utility also originally proposed:
- that campground sites be charged at 0.18 units per site per
annum;
- that existing residential properties greater than 100 meters
from the main be exempt from the residential demand and flow charges; and
- that only 84 campground sites in the Marco Polo Land
campground be required to connect to the sewer system.
As a result of revisions made to the original application,
the utility now proposes:
- An annual frontage rate of $1.00 per foot - to a maximum of
$500 - with a 100 foot exemption for each proportionate unit charged the customer;
- an annual customer charge of $102.04 for each customer;
- an annual demand charge of $88.00 per proportionate unit;
and
- a flow charge of $0.78 per cubic meter.
The revised rates are based on the following expense
estimates and allocation of costs:
Table 2
Cavendish Sewer Utility
Revised Allocation of Expenses and Rate Proposals
The utility also now proposes:
- that campground sites be charged at 0.10 units per site per
annum;
- that existing residential properties greater than 100 meters
from the main be exempt from the residential demand and flow charges;
- that only 84 campground sites in the Marco Polo Land
campground be required to connect to the sewer system;
- that non-leased farm land actively used for farming be
exempted from all Tariff charges; and
- that the Cavendish Cemetery be exempted from all Tariff
charges.
In a written submission to the Commission dated March 30,
1994 (Exhibit 23), the revisions to the original submission are described by the utility:
Capital recovery is reduced to reflect a mortgage rate of
7.5% [7.25%] amortized over 25 years. The mortgage period is 5 years. The principal amount
is $475,000.
Electrical costs are based on an amended study by Malcolm
Lodge for UMA Engineering.
System operation and maintenance costs are based on a
maintenance contract plus recalculated Engineering estimates.
Administration costs reflect contracting out book keeping
and renegotiation with the community.
The additional purchase of land to compensate Parks Canada
totaling $140,000 has been put on hold...
The revised campground site rate of .10 of a sewer unit
was established as a result of negotiations with the campground owners.
(Exhibit 23, p.1)
4. Findings
The Cavendish sewer system represents a significant capital
investment in the long-term economic welfare of this resort community. The likelihood of
sewage-related environmental problems and their probable impact on the tourism industry in
this area have, with the installation of the sanitary sewer system, been largely
eliminated.
This long-term benefit to the community comes, of course,
at a cost. Even with federal and provincial capital grant assistance approaching the 80%
level and the arrangement with Parks Canada to defer a land purchase, capital-related
costs to the end-user still represent some 50% of the total annual cost of operating the
system. With such a small customer base, user-rates will remain highly sensitive to change
in costs. For example, an increase in costs of $15,000 a year would increase the proposed
revenue requirement and rates by some 17%. Given the relatively high proposed rate levels,
efforts must continue to be made to keep costs to an absolute minimum and, where possible,
to reduce them. We are confident the utility will continue to explore ways and means of
doing so.
While the specific rate proposals of the applicant are
somewhat more complex than that of other utilities, the unique and seasonal nature of the
customer base combined with the consultation process that the applicant has had with its
customers leads us to conclude that the proposed rate-design methodology should be
approved. If, at a later date, the methodology proves to be overly complicated in terms of
the customers' understanding of the rates, we will consider the possibility of simplifying
the Tariff.
The Commission notes that the matter of an appropriate unit
value to assign to campground sites will not be resolved until we have available
additional flow data. We will revisit this issue at a later date. In the meantime, the
unit value of 0.10 units per campsite will receive interim approval.
The applicant's audited financial statements for the year
ended December 31, 1993 show a deficit of $13,000. Since this deficit must be recovered
from rates, we have added $5,000 to the utility's annual revenue requirement to reflect
the recovery of this deficit, including interest, over a three-year period. The revised
revenue requirement and resulting customer rates are shown on Table 3.
Table 3
Cavendish Sewer Utility
Approved Allocation of Expenses and Authorized Rates
The above rates will be approved, on an interim basis. In
addition, the exemptions proposed by the applicant have been reviewed by the Commission
and will, at this time, be allowed. We will revisit this issue when the applicant next
appears before us.
Finally, the Commission wishes to acknowledge the efforts
of the utility and, in particular, its Chair, Walter Wyand, for his work in attempting to
resolve many of the issues earlier raised by customers. We also acknowledge and thank the
other hearing participants for their contributions to the review process and those who
provided us with written comments.
5. Disposition
An order granting interim approval to the Tariff appended
hereto will therefore issue. The Tariff shall have effect from January 1, 1994 and will be
subject to review and confirmation in the first quarter of 1996. The applicant shall
provide the Commission with actual customer flow data by November 30 of each year.
Order
UPON the
application of the Cavendish Sewer Utility (the "utility") for interim approval
of a Tariff for sanitary sewer services;
AND UPON hearing and considering submissions made by the utility and
interveners at public hearings conducted in Charlottetown on November 10, 1993 and June 9,
1994 after due public notice;
AND UPON it appearing to the Commission that the Tariff authorized herein is
not unreasonable or unjustly discriminatory;
NOW THEREFORE,
for the Reasons given in the annexed Reasons for Order;
IT IS ORDERED THAT
1. Interim approval is hereby granted to the utility for
the implementation of the Tariff appended to, and forming part of, this Order;
2. The appended Tariff is declared effective on January
1, 1994 and shall remain in effect until otherwise ordered by the Commission;
3. The utility shall file with the Commission, by
February 15, 1996, an application for confirmation of the interim rates approved herein;
and
4. Until otherwise ordered, the utility shall file with
the Commission, by November 30 of each year, actual flow data for each metered customer
for the current year.
DATED at
Charlottetown, Prince Edward Island, this 23rd day of June, 1994.
BY THE COMMISSION:
Linda Webber, Chair
John L. Blakney, Vice-Chair
Deborah MacLellan, Commissioner
NOTICE
Section 12 of the Island Regulatory and Appeals
Commission Act reads as follows:
12. The Commission may, in its absolute discretion,
review, rescind or vary any order or decision made by it or rehear any application before
deciding it.
Parties to this proceeding seeking a review of the
Commission's decision or order in this matter may do so by filing with the Commission, at
the earliest date, a written Request for Review, which clearly states the reasons
for the review and the nature of the relief sought.
Sections 13.(1) and 13(2) of the Act provide
as follows:
13.(1) An appeal lies from a decision or order of the
Commission to the Appeal Division of the Supreme Court upon a question of law or
jurisdiction.
(2) The appeal shall be made by filing a notice of appeal
in the Supreme Court within twenty days after the decision or order appealed from and the
Civil Procedure Rules respecting appeals apply with the necessary changes.