Docket UW31401.2
Order UW95-3
IN THE MATTER of a dispute
between Brian MacDonald and the North River Water and Sewer Utility Corporation.
BEFORE THE COMMISSION
on Tuesday, the 28th day of March, 1995.
Linda Webber, Chair
John L. Blakney, Vice-Chair
Anne McPhee, Commissioner
Order
WHEREAS:
On December 16, 1994, Brian MacDonald lodged a complaint
with the Commission concerning a bill he received from the North River Water and Sewer
Utility Corporation (the "utility") associated with the costs of sewer main
construction carried out in front of lots owned by Mr. MacDonald on MacRae Drive in the
Community of North River. Mr. MacDonald submits that the costs should be the
responsibility of the utility. The utility submits that the costs are properly the
responsibility of Mr. MacDonald.
At issue is the cost of main line construction carried out
in 1994 along lots 19, 23 and 25 on MacRae Drive that were developed by Mr. MacDonald in
the late 1980s-early 1990s. According to Mr. MacDonald, the lots in question were part of
a subdivision plan approved by the community in 1987 and that, since this approval was
issued prior to the approval of the core plan, the lots should have been included in the
plan. The utility, on the other hand, submits that the lots were not developed at the time
the core plan was submitted for approval and therefore were properly excluded from the
plan.
A review of the core plans approved by the former Public
Utilities Commission in 1987 and revised in 1989 confirms that the lots in question were
outside the approved core-area plan. We understand that our colleagues of the day followed
the practice of only including in a plan existing built-up or developed areas and not
those either planned or approved for future development unless some special or unusual
circumstance existed. The fact that the MacRae Drive extension was not included in the
core plan would therefore not appear unusual. The mere existence of an approved
subdivision plan does not, in and of itself, mean that development will occur.
While the Commission sympathizes with Mr. MacDonald now
being confronted with a bill for lots he developed some time ago, it is clear from the
development permits for the lots in question that he knew of this requirement prior to
actual development. Moreover, since there is nothing before us to indicate that the
utility in any way misled Mr. MacDonald or improperly applied the rules and regulations of
the day, we are unable to find anything other than the utility acted properly and has the
right to require payment.
On the issue of the actual costs associated with the sewer
extension, we understand that the basis of the costbefore adjustment for grants and
the 10% utility contributionis a letter dated December 15, 1994 from P.S. Hughes of
CBCL Limited to Mr. Sentner, the utility's administrator. As we understand it, Mr.
Hughes has calculated the pro-rated cost of a larger project at $22,325 for some 300 feet
of servicing, including service laterals. This equates to an average cost of $74.42 per
foot.
A review of Mr. Hughes' figures indicates that the costs of
the extension in question are higher than the average cost of some 3000 feet of other
sewer construction carried out during the same period in 1994. An earlier estimate
prepared by Mr. Sentner shows a cost of $17,280, some 30% lower than the cost estimate
prepared by Mr. Hughes. This equates to an average cost of $57.60 per foot.
Without the benefit of a more detailed estimate and
explanation for the higher-than-average cost calculated by Mr. Hughes, the Commission is
inclined to accept the average cost calculated by Mr. Sentner. In our view, Mr.
Sentner's initial calculation of the costs is a fairer representation of actual costs
of servicing typical subdivision lots and should be applied to the formula for calculating
the amount payable by Mr. MacDonald.
Capital Costs |
$17,280.00 |
Less Infrastructure grant @ 40% |
6,912.00 |
Net Cost |
$10,368.00 |
Less Utility Contribution @ 10% |
1,036.80 |
Total Developer Cost |
$ 9,331.20 |
Cost assigned to B. MacDonald
(50%) |
$ 4,665.60 |
In conclusion, therefore, we find that the utility's
actions in this matter were proper and that the amount of $9,331.20 is properly allocated
to the developers. Of this, the amount of $4,665.60 is the responsibility of Brian
MacDonald.
The foregoing is
SO
ORDERED.
DATED at
Charlottetown, Prince Edward Island, this 28th day of March, 1995.
BY THE COMMISSION:
Linda Webber, Chair
John L. Blakney, Vice-Chair
Anne McPhee, Commissioner
NOTICE
Section 12 of the Island Regulatory and Appeals
Commission Act reads as follows:
12. The Commission may, in its absolute discretion,
review, rescind or vary any order or decision made by it or rehear any application before
deciding it.
Parties to this proceeding seeking a review of the
Commission's decision or order in this matter may do so by filing with the Commission, at
the earliest date, a written Request for Review, which clearly states the reasons
for the review and the nature of the relief sought.
Sections 13.(1) and 13(2) of the Act provide
as follows:
13.(1) An appeal lies from a decision or order of the
Commission to the Appeal Division of the Supreme Court upon a question of law or
jurisdiction.
(2) The appeal shall be made by filing a notice of appeal
in the Supreme Court within twenty days after the decision or order appealed from and the
Civil Procedure Rules respecting appeals apply with the necessary changes.