Docket UE20706
Order UE92-6
IN THE MATTER
of an application of Maritime Electric
Company, Limited for approval of the Company's 1992 Capital Programs.
BEFORE THE COMMISSION
on Monday, the 3rd day of August, 1992.
Linda Webber, Chairman
John L. Blakney, Vice-Chairman
Order
Contents
Appearances & Witnesses
Reasons for Order
1 Introduction
2 The Application
2.1 Program Summary
2.2 Demand Side Management
2.3 General Expenditures
2.4 Production
2.5 City Distribution
2.6 Rural Distribution
2.7 Transmission
2.8 Capitalized General Expenses
3 Other Matters
3.1 Proposed Amendments to 1990 & 1992 Capital Programs
3.2 Supplementary Capital Items-1990
Order
Appearances & Witnesses
1. For Maritime Electric Company, Limited
Counsel:
William G. Lea
Witnesses:
P.H. Newcombe, Vice-President, Engineering and Operations
J.A. Lea, Vice-President, Customer Service and Energy Management
James Landrigan, Manager, Transmission & Distribution
E.B. MacKay, Manager, Administration
2. For the Minister of Energy & Forestry, Government of Prince
Edward Island
Counsel:
Shauna Sullivan-Curley
J. Gordon MacKay
3. For The Island Regulatory and Appeals Commission
Counsel:
Thomas A. Matheson
Staff:
Donald G. Sutherland
Director, Utilities Division
Heather Walker & Joan MacKay
Recording Secretaries
Reasons for Order
1 Introduction
This is an application by Maritime Electric Company, Limited (the
"Applicant" or "Company") for approval of the Company's 1992 capital
programs. The application, which was filed with the former Public Utilities Commission on
October 16, 1991, was heard in public before this Commission on November 21 and 22, 1991
and February 10, 11 and 14, 1992, after due public notice. An intervention in this case
was entered by the Minister of Energy and Forestry, Government of Prince Edward Island
(the "Minister" or "Government").
2 The Application
2.1 Summary
Table 1 shows a summary of the major account items submitted to the
Commission for approval.
Table 1
Summary of 1992 Capital Programs
Major Account |
Amount |
Demand Side Management |
$ 880,750 |
General |
125,000 |
Production |
5,458,000 |
City Distribution |
1,434,000 |
Rural Distribution |
3,560,000 |
Transmission |
325,000 |
|
$11,782,750 |
Capitalized General Expenses |
1,822,000 |
Total |
$13,604,750 |
|
|
Contributions |
|
Demand Side Management |
30,750 |
City Distribution |
97,400 |
Rural Distribution |
375,000 |
|
503,150 |
Net Total |
$ 13,101,600 |
2.2 Demand Side Management
Specific Demand Side Management (DSM) Programs proposed in this
application are set out in Table 2.
Table 2
1992 Demand Side Management Programs
Item |
Program |
Amount |
DSM-1 |
Residential Compact Fluorescent Lamps |
$ 58,150 |
DSM-2 |
Residential Krypton Bulb Program |
59,800 |
DSM-3 |
Residential Hot Water Conservation |
132,000 |
DSM-4 |
Refrigerator Rebate |
165,000 |
DSM-5 |
Farm Compact Fluorescent Lamps |
55,300 |
DSM-6 |
Farm Fluorescent Lighting |
53,100 |
DSM-7 |
Farm High Efficiency Motors |
95,000 |
DSM-8 |
Commercial Compact Fluorescent Lamps |
28,400 |
DSM-9 |
Commercial Fluorescent Lighting |
114,000 |
DSM-10 |
Commercial High Efficiency Motors |
120,000 |
|
Total |
$ 880,750 |
|
|
|
|
Contributions |
|
DSM-1 |
Residential Compact Fluorescent Lamps |
18,750 |
DSM-3 |
Residential Hot Water Conservation |
12,000 |
|
|
30,750 |
|
|
|
|
Net Total |
$ 850,000 |
In addition to the specific DSM programs proposed in this application, the Company
proposes an amortization period for each program based on the program's estimated useful
life.
The Commission continues to view DSM initiatives as essential elements
of the Company's activities. To this end, the Commission encourages the Company to
continue to explore new and innovative approaches to the management of system demand in an
effort to reduce, over time, the rate of load growth and the need to acquire new
generation.
The Company's 1992 DSM proposals are approved. The Company is expected
to continue to treat DSM as one of its highest priorities.
1. The following 1992 DSM programs and amortization periods are
approved:
Item Program Amount Amortization Period
DSM-1 Res. Compact Fluorescent Lamps $ 58,150 4 Yrs
DSM-2 Res. Krypton Bulbs $ 59,800 3 Yrs
DSM-3 Res. Hot Water Conservation $132,000 12 Yrs
DSM-4 Refrigerator Rebate $165,000 15 Yrs
DSM-5 Farm Compact Fluorescent Lamps $ 55,300 4 Yrs
DSM-6 Farm Fluorescent Lighting $ 53,100 12 Yrs
DSM-7 Farm High Efficiency Motors $ 95,000 10 Yrs
DSM-8 Commercial Compact Fluor. Lamps $ 28,400 4 Yrs
DSM-9 Commercial Fluor. Lighting $114,000 12 Yrs
DSM-10 Commercial High Eff. Motors $120,000 12 Yrs
2.3 General Expenditures
General Capital Items proposed for 1992 are shown in Table 3.
Table 3
1992 General Items
Item |
Program |
Amount |
G-1 |
Insulation & Siding - Head Office |
55,000 |
G-2 |
Office Equipment & Furniture |
20,000 |
G-3 |
Management Information Systems |
50,000 |
|
|
|
|
Total |
$ 125,000 |
Item G-3-Management Information Systems-includes an expenditure of $34,000 for terminal
servers and modems for enhancing communications with the Company's district offices as
well as an expenditure of $16,000 for computer workstations. The Company notes in its
application that it is studying the need for additional expenditures of some $435,000 for
an upgrade to its central computing facility and related computing and printing equipment.
During the hearing, it became apparent to the Commission that the
information systems area of the Company is in need of a comprehensive review. Questions
posed to Company witnesses indicate that long-range planning in this area is effectively
absent. This situation must be rectified.
2. The Company shall prepare and file with the Commission, at the
earliest date, a comprehensive study into the Company's long-range information systems
needs.
3. The study in 2 shall include, but not be limited to, a minimum
five-year needs analysis together with an implementation plan.
4. The proposed 1992 information systems expenditures totaling
$50,000 are approved; however, additional expenditures-including supplementary budget
requests-will not be authorized pending review of the above information systems study.
5. Other 1992 general expenditures of $75,000 are approved.
2.4 Production
Production Expenditures proposed for 1992 are shown in Table 4.
Table 4
1992 Production Programs
Item |
Program |
Amount |
P-1 |
Misc. Mechanical Equipment |
5,000 |
P-2 |
Misc. Electrical Equipment |
3,000 |
P-3 |
Engineering & Test Equipment |
40,000 |
P-4 |
Machine Shop Lathe & Press |
65,000 |
P-5 |
Dalhousie Capital Additions |
5,000 |
P-6 |
Steam Plant Life Extension |
5,000,000 |
P-7 |
Generation Planning Studies |
100,000 |
P-8 |
Communications System |
50,000 |
P-9 |
Supervisory System |
2,000 |
P-10 |
Steam Plant Property Improvements |
100,000 |
P-11 |
Air Conditioner for No. 4 Boiler Area |
3,000 |
P-12 |
Sump Pump, Main Oil Tank Const. Area |
15,000 |
P-13 |
Replacement Battery - West Royalty & Borden |
20,000 |
P-14 |
Snow Hoods for No. 1 Gas Turbine |
50,000 |
|
|
|
|
Total |
$ 5,458,000 |
These expenditures have been reviewed by the Commission and are approved. The Company
shall continue to update the Commission on the steam plant life extension program.
6. 1992 Production Expenditures totaling $5,458,000 are approved.
2.5 City Distribution
Proposed 1992 City Distribution Expenditures are shown in Table 5.
Table 5
1992 City Distribution Programs
Item |
Program |
Amount |
C-1 |
SCFD* Replacements |
10,000 |
C-2 |
Street Alteration Rebuilds |
20,000 |
C-3 |
Distribution Transformers |
200,000 |
C-4 |
Service Lines |
40,000 |
C-5 |
Service Line Upgrades |
40,000 |
C-6 |
Street and Yard Lighting |
45,000 |
C-7 |
Distribution Line Extensions |
25,000 |
C-8 |
Distribution Line Rebuilds |
15,000 |
C-9 |
System Meters |
350,000 |
C-10 |
Line Tools |
25,000 |
C-11 |
Engineering & Test Equipment |
10,000 |
C-12 |
Transportation Equipment |
370,000 |
C-13 |
Rebuilds Due to Joint Use |
5,000 |
C-14 |
Transformer Shop Equipment |
2,000 |
C-15 |
Meter Shop Equipment |
2,000 |
C-16 |
Job Order Transfers |
75,000 |
C-17 |
Hazardous Waste Facility |
200,000 |
|
Total |
$ 1,434,000 |
|
|
|
|
Contributions |
|
|
City Service Lines - New (44%) |
17,600 |
|
City Service Lines - Replacements (12%) |
4,800 |
|
Job Order Transfers (100%) |
75,000 |
|
|
97,400 |
|
|
|
|
Net Total |
$ 1,336,600 |
*Storm, Fire, Collision & Deterioration
The City Distribution Budget is approved. A discussion on the need for a
review of the Company's customer contribution schedules is contained in Section 2.6 of
these reasons.
7. 1992 City Distribution Expenditures totaling $1,434,000 are
approved.
2.6 Rural Distribution
1992 Rural Distribution Expenditures are shown in Table 6.
Table 6
1992 Rural Distribution Programs
Item |
Program |
Amount |
R-1 |
SCFD Replacements |
100,000 |
R-2 |
Road Alteration Rebuilds |
10,000 |
R-3 |
Distribution Transformers |
550,000 |
R-4 |
Service Lines |
440,000 |
R-5 |
Service Line Upgrades |
250,000 |
R-6 |
Street and Yard Lighting |
80,000 |
R-7 |
Distribution Line Extensions |
150,000 |
R-8 |
Line Rebuilds & Improvements |
530,000 |
R-9 |
Line Control Devices |
20,000 |
R-10 |
Rebuilds due to Joint Use |
50,000 |
R-11 |
Job Order Transfers |
100,000 |
R-12 |
Pole Replacement Program |
1,280,000 |
|
Total |
$ 3,560,000 |
|
|
|
|
Contributions |
|
|
Service Lines - New (50%) |
220,000 |
|
Service Lines - Upgrades (19%) |
47,500 |
|
Extensions (19%) |
7,500 |
|
Job Order Transfers (100%) |
100,000 |
|
|
375,000 |
|
|
|
|
Net Total |
$ 3,185,000 |
In Order E91-4 dated June 26, 1992, the Public Utilities Commission ("PUC")
reviewed the Company's 1991 capital programs and ordered, among other things, that the
Company file additional evidence supporting budget items R - 8-Rural Line Rebuilds and
Improvements and item R-12-Pole Replacement Program. The PUC's filing requirement was
based on the following expressed concern:
Although Company witness Newcombe gave additional evidence on this
topic [items R-8 and R-12] and later filed supplementary information, the Commission
believes that the proposal to further reduce the level of expenditures is...unsupported.1
Exhibit A-6 in this docket is the Company's response to the PUC Order.
This was supplemented at the hearing by the filing of Exhibit A-10, a report of the
Company entitled DISTRIBUTION: Pole Replacement and Rural Rebuild, February 1992.
The Commission has reviewed the submissions of the Company on the issue
and wants it clearly understood that poles and conductors in the Company's rural
distribution system must not be allowed to return to the condition they were in in the
early 1980's. Although we accept at this time the Company's position that the overall
rural distribution system is in good condition, we remain concerned that the Company may
sacrifice needed work on the system in favor of other capital projects.
The Commission notes that the Company has commenced the filing of a
monthly Outage Statistics Report that should, over time, allow the
Commission-and indeed the management of the Company-to more effectively monitor the
Company's system in terms of system reliability. Although this report should help identify
potential problem areas, it is not viewed as a substitute for a systematic program of pole
and line replacements and rebuilds. The Commission will expect the Company to continue to
refine its distribution planning methodology and to demonstrate, on an annual basis, that
annual expenditures for line rebuilds and improvements and the Company's pole replacement
program are adequate. The Commission will also expect the Company to improve
communications with its field personnel over the reporting of non-critical problem areas
in the Company's distribution system. Based on the evidence presented at the hearing, we
are left with the impression that a formal reporting system for such problems is not in
place.
Having considered all of the Company's submissions on 1992 rural
distribution proposals,
8. 1992 Rural Distribution Expenditures totaling $3,560,000 are
approved.
The Commission has been aware for some time and the Company has
acknowledged that the Company's customer contribution schedules and policies are in need
of review. We understand that such a review was commenced in 1988 by the PUC but later
abandoned in favor of more pressing issues. We are also advised by Commission staff that
the Company recently suggested that the matter be revisited. We agree.
The Company is directed to undertake a review of this matter and to file
a report thereon with the Commission by mid-December of this year. The report should
contain recommendations on changes to the contribution schedules and policies with the
view of ensuring that the schedules and policies are fair and equitable to the Company and
its customers.
A public review of the matter will be conducted in early 1993. An order
mandating the above review is not considered necessary.
2.7 Transmission
1992 proposed transmission expenditures are shown on Table 7.
Table 7
1992 Rural Transmission Programs
Item |
Program |
Amount |
T-1 |
SFCD Replacements |
$ 10,000 |
T-2 |
Rebuilds due to road construction |
10,000 |
T-3 |
Rebuild Victoria Cross substation |
180,000 |
T-4 |
Power transformer radiators |
35,000 |
T-5 |
Protection additions |
15,000 |
T-6 |
Transmission planning study |
75,000 |
|
|
|
|
Total |
$ 325,000 |
The proposals have been reviewed by the Commission and approved.
7. Transmission expenditures totaling $325,000 in 1992 are
approved.
2.8 Capitalized General Expenses
General expense-capital represents general overheads associated with
capital items to be installed or constructed in 1992 that the Company proposes to
capitalize.
The Commission notes that the Company does not strictly adhere to NARUC2
guidelines relating to the capitalization of general overheads. These guidelines specify,
among other things, that a Utility should undertake periodic studies at least one a year
on the proportion of an employee's time that is includible in capital accounts. According
to Counsel for the Company, Mr. Lea:
I am advised that although not all departments of Maritime Electric
examine the allocation of administrative costs to capital annually an effort is made to
re-examine the allocations from time to time and, where a significant change in the amount
of capital-related activity occurs, an analysis of the associated costs is carried out.3
A review of this account over the last several years and the manner in
which it has fluctuated4 leads the Commission to believe that strict adherence
to the NARUC guidelines is necessary.
The Company's 1992 proposal will be approved. However,
8. The Company shall hereinafter strictly comply with the NARUC
guidelines respecting the allocation and treatment of administrative and general expenses
to be capitalized.
9. 1992 capitalized general and administrative expenses totaling
$1,822,000 are approved.
3 Other Matters
3.1 Proposed Amendments to 1990 and 1991 Capital Programs
The Company seeks approval of amendments to its PUC-approved 1990 and
1991 capital programs. Specifically, the Company seeks approval
- of additional expenditures of $561,238.63 associated with the Company's
head office at 180 Kent Street, Charlottetown; and
- of additional expenditures of $417,665.00 associated with the Company's
West Royalty Service Center.
The properties in question have been the subject of extensive discussion
and debate before the PUC since 1989. The economics of the Company's decision to purchase
and renovate these properties has, we believe, been adequately reviewed and the Commission
is satisfied that, even with the capital additions proposed herein, the acquisition of
these properties remains within the best long-term interests of the Company's customers.
The proposals are approved. However, we want to caution the Company on
the need to seek, in a timely fashion, regulatory approval of capital expenditures. The
Commission does not wish to see a repeat of the difficulties encountered in reviewing,
after the fact, expenditures such as those considered herein.
10. Additional capital expenditures of $561,238.63 associated with
the Company's head office at 180 Kent Street, Charlottetown and $417,665.00 associated
with the Company's West Royalty Service Center are approved as at December 31, 1991.
During the hearing, the Company was asked to outline the status of the
Company's former head office at 134 Kent Street-a leased property which remains vacant.
The Company noted that efforts have and continue to be made to sub-lease the property.
In order to monitor the Company's activities in this area,
11. The Company is directed to file, in conjunction with its 1993
capital programs application, a detailed report of its efforts to sub-lease the former
head office property at 134 Kent Street, Charlottetown.
3.2 Supplementary Capital Items-1990
These items have been reviewed by the Commission and are approved.
12. 1990 supplementary capital expenditures set out in section 4
of the application are approved.
An Order will therefore issue.
IN THE MATTER of an application of Maritime
Electric Company, Limited for approval of the Company's 1992 Capital Programs.
Order
WHEREAS Maritime Electric Company, Limited (the "Company"), by application
filed with the former Public Utilities Commission on October 16, 1991, applied for
approval of the Company's 1992 capital programs;
AND WHEREAS the Island Regulatory and Appeals Commission ("Commission") heard the
application at public hearings conducted in Charlottetown on November 21 and 22, 1991 and
February 10, 11 and 14, 1992 after due public notice;
AND WHEREAS the Commission has issued its findings in this matter in accordance with the
Reasons for Order issued with this Order;
NOW THEREFORE, pursuant to the Island Regulatory and
Appeals Commission Act and the Electric Power and Telephone Act;
IT IS ORDERED THAT
1. The following 1992 DSM programs and amortization periods are
approved:
|
|
|
Amortization |
Item |
Program |
Amount |
Period |
|
|
|
|
DSM-1 |
Res. Compact Fluorescent Lamps |
$ 58,150 |
4 Yrs |
DSM-2 |
Res. Krypton Bulbs |
$ 59,800 |
3 Yrs |
DSM-3 |
Res. Hot Water Conservation |
$132,000 |
12 Yrs |
DSM-4 |
Refrigerator Rebate |
$165,000 |
15 Yrs |
DSM-5 |
Farm Compact Fluorescent Lamps |
$ 55,300 |
4 Yrs |
DSM-6 |
Farm Fluorescent Lighting |
$ 53,100 |
12 Yrs |
DSM-7 |
Farm High Efficiency Motors |
$ 95,000 |
10 Yrs |
DSM-8 |
Commercial Compact Fluor. Lamps |
$ 28,400 |
4 Yrs |
DSM-9 |
Commercial Fluor. Lighting |
$114,000 |
12 Yrs |
DSM-10 |
Commercial High Eff. Motors |
$120,000 |
12 Yrs |
2. The Company shall prepare and file with the Commission, at the
earliest date, a comprehensive study into the Company's long-range information systems
needs.
3. The study in 2 shall include, but not be limited to, a minimum
five-year needs analysis together with an implementation plan.
4. The proposed 1992 information systems expenditures totaling
$50,000 are approved; however, additional expenditures will not be authorized pending
review of the above information systems study.
5. Other 1992 general expenditures of $75,000 are approved.
6. 1992 Production Expenditures totaling $5,458,000 are approved.
7. Transmission expenditures totaling $325,000 in 1992 are approved.
8. The Company shall hereinafter strictly comply with the NARUC
guidelines respecting the allocation and treatment of administrative and general expenses
to be capitalized.
9. 1992 capitalized general and administrative expenses totaling
$1,822,000 are approved.
10. Additional capital expenditures of $561,238.63 associated with
the Company's head office at 180 Kent Street, Charlottetown and $417,665.00 associated
with the Company's West Royalty Service Center are approved as at December 31, 1991.
11. The Company is directed to file, in conjunction with its 1993
capital programs application, a detailed report of its efforts to sub-lease the former
head office property at 134 Kent Street, Charlottetown. And
12. 1990 supplementary capital expenditures set out in section 4 of
the application are approved.
DATED at Charlottetown, Prince Edward Island, this 3rd day of
August, 1992.
BY THE COMMISSION:
Linda Webber, Chairman
John L. Blakney, Vice-Chairman
1 Public Utilities Commission Order E91-4 in Docket E20705
(June 26, 1992), p.9.
2 National Association of Regulatory Utility Commissioners.
3 Letter to Commission from William G. Lea, dated April 6,
1992.
4 These fluctuations appeared to be related, in part, to time
allocation difficulties.