Click here for a PDF version of
this Order.
Docket
UE20940
Order UE10-03
IN
THE MATTER
of an application by Maritime Electric Company, Limited for
approval of amendments to rates, tolls and charges.
BEFORE THE
COMMISSION
on
Monday, the 12th day of July, 2010.
Maurice
Rodgerson, Chair
John Broderick, Commissioner
Anne Petley, Commissioner
Ernest Arsenault, Commissioner
Order
Contents
Appearances & Witnesses
Reasons for Order
1. Introduction & Background
2. The Application
3. Discussion
3.1 Intervener - PEI Senior Citizens' Federation
3.2 Intervener - John te Raa
3.3 Intervener - ECO PEI
3.4 Intervener - Government of PEI
3.5 Members of the Public
3.6 Applicant - Maritime Electric Company, Limited
4. Findings
4.1 Point
Lepreau Replacement Energy
4.2 ECAM Rebasing and Amortization Period
4.3
2nd Block Tariff and Rate Design
4.5 Rate of Return
4.4 Revenue Requirement and Other Matters
5. Disposition
Order
Appearances & Witnesses
1. For Maritime Electric
Company, Limited
Counsel:
Spencer Campbell
Thomas Laughlin
Witnesses:
Fred J. O'Brien, President & Chief Executive Officer
John D. Gaudet, Vice President, Corporate Planning & Energy Supply
J. William Geldert, Vice President, Finance & Administration, Chief
Financial Officer & Corporate Secretary
Steven D. Loggie, Vice President, Customer Service
Kathleen C. McShane, Consultant, Foster Associates, Inc.
2. For the Minister of
Environment, Energy & Forestry, Government of Prince Edward Island
Counsel:
J. Gordon MacKay
Witnesses:
Laurence D. Booth, Consultant
Wayne MacQuarrie, PEI Energy Corporation
3. Interveners
Roger King, PEI Senior
Citizens' Federation
Matthew MacCarville, Environmental Coalition of PEI
John teRaa, Private Citizen
4. Public Participants
Ernest Mutch & John
Jamieson, PEI Federation of Agriculture
Elwin Wyand, Edith Ling, Douglas Campbell and David Best, National
Farmers Union District 1, Region 1
Harold MacNevin, Dairy Farmers of Prince Edward Island
5. For The Island Regulatory
and Appeals Commission
Counsel:
Ryan P. MacDonald
Staff:
Allison MacEwen, Director, Technical & Regulatory Services
Mark Lanigan, Senior Analyst, Technical & Regulatory Services
Linda Allen, Recording Secretary
Reasons for Order
1. Introduction &
Background
[1] This is an application
under the
Electric Power Act,
R.S.P.E.I. 1988, Cap. E-4, by Maritime Electric Company, Limited (the
"Applicant", "Maritime Electric" or the "Company") seeking, among other
things, an Order or Orders of the Island Regulatory and Appeals Commission
(the "Commission") approving amendments to the rates, tolls and charges for
electric service for the period beginning August 1, 2010, and
reconsideration of the 2nd block rate elimination.
[2] The Application was
filed pursuant to Section 20(1) of the
Electric Power Act,
(the "Act")
which reads as follows:
Variation of
rates, submission for review and approval |
20. (1) Whenever
any public utility wishes to vary any existing rates, tolls or
charges, or to establish any new rates, tolls or charges for any
service, it shall submit for the review and approval of the
Commission a schedule of such proposed rates, tolls and charges
together with and appended thereto all rules and regulations which,
in any manner, relate to the rates, tolls and charges; the
Commission may approve, after reviewing the schedule and rules and
regulations submitted, the schedule of rates, tolls and charges and
the rules and regulations either in whole or in part, or may
determine and fix new rates, tolls and charges, and amend the rules
and regulations as it sees fit.
2003,c.3.s.10. |
[3] The Company's
original application filed with the Commission on January 29, 2010 requested
the following:
-
Approval to rebase the
Energy Cost Adjustment Mechanism ("ECAM") which would increase the base
charge for energy to $0.0940/kWh in 2010 and $0.0960/kWh effective April
1, 2011;
-
Permission to file an
updated report on ECAM rebasing to the Commission by November 30, 2010;
-
Approval to continue the
Point Lepreau replacement energy deferral, as well as approval of a
25-year amortization period for deferred replacement energy costs,
beginning with the return to service expected March 1, 2011; and
-
Approval of a maximum
allowed Return on Average Common Equity of 9.75 per cent for 2010 and
2011.
[4] In February, 2010 the
Commission published a Notice of Application in local newspapers seeking
public input. The following summarizes the responses received:
The PEI Senior Citizens'
Federation and affiliate senior clubs across PEI filed petitions signed
by members of each local club stating:
"We the undersigned
request that IRAC hold a public hearing to review the 2010 Rate
Change Application submitted by Maritime Electric."
In addition, several of the
petitions included letters from seniors which provided various comments such
as:
-
the need for MECL to use
time-of-day rates;
-
the Company should be
required to "think outside the box and use more hydro, nuclear and wind
power";
-
a public hearing like last
year's would be useful to assist with their understanding;
-
concerns about the
refurbishment of Point Lepreau, replacement energy costs and rate
implications;
-
the elimination of the
second block and the lack of information on the impact on certain
customers; and
-
energy charge increases and
the Company's conflicting statement of no cost increases in 2010.
The Federation of Agriculture
provided correspondence on March 4, 2010 stating that the current
application, along with a previously issued IRAC Order (UE08-01), have
implications for the agricultural sector on PEI. The Federation suggested
that a public hearing be held where they could participate and present their
concerns.
The Commission received either
directly, or via copy, three pieces of correspondence from Mr. John te Raa.
The correspondence contained questions and referenced the need for full
consideration of the true cost of electricity in setting rates. No mention
was made regarding the requirement to hold a public hearing.
Mr. Roger King filed two emails
with the Commission. His first email indicated that the Company's rate
application is written in a confusing manner, does not explicitly state the
rate changes proposed, and that the Company does not "think outside the
box". Mr. King also stated that electric heat is the most efficient and is
more environmentally-friendly, and that a combination of in-floor and
domestic hot water heating with a "time of day" tariff is one obvious
alternative to a second block rate. As well, he requested a public hearing
be held to allow for full public input.
In his second email, Mr. King
provided comments on Commission Order
UE08-01 suggesting that the wording is
unclear. He also stated that the elimination of the declining block is just
one issue of many "requests for change" in the 2010 application that affect
customers in both the short and long term. Mr. King concluded his email by
stating that "a public hearing is necessary to have all public issues
resolved where facts are sorted from fiction andIslanders are told one
common and correct story".
Ira Smith provided a letter to
the Commission expressing concern and support regarding the continuation of
the Point Lepreau replacement energy deferral. Also, she stated the cost of
the replacement energy and refurbishment costs should be incurred by today's
consumers and not our children and grandchildren.
The Province of PEI, by letter
dated February 19, 2010, filed a Notice of Intervention and requested the
Commission schedule a public hearing for the purpose of the presentation of
oral evidence with respect to this application. The Province also filed a
series of interrogatories with respect to this application.
On March 2, 2010 the Hon.
Richard Brown, Minister of Environment, Energy and Forestry, wrote the
Commission requesting the Commission review and rescind Order
UE08-01 with
regard to the elimination of the reduced second block rate.
In addition, on March 5, 2010
Maritime Electric wrote the Commission seeking approval to suspend the
implementation of
UE08-01 based on the following reasons:
-
Discussion between
Governments of PEI and Quebec concerning a potential energy supply
agreement which would change electricity pricing in PEI beyond a reduced
second block;
-
The need for a further cost
allocation study which may impact all rates;
-
Further development of an
updated Demand Side Management plan ("DSM"); and
-
Reconsideration of the
reduced second block as part of the pending 2010 rate application will
allow all interested parties, who have expressed concerns about the
public awareness and lack of consultation of the reduced second block
elimination, an opportunity to make their views and evidence known to
the Commission.
[5] The Commission issued
Order
UE10-01 on March 9, 2010 which delayed the final step in the
elimination of the second block rate, directed the Company to file further
information on this issue, and instructed the Company that the 2nd block
tariff would be reviewed as part of the 2010 rate application.
[6] Following the
significant public interest in this application, in April, 2010, the
Commission published a notice in local newspapers inviting parties to
participate in a public hearing. Anyone interested in participating as an
intervener was advised to file a Notice of Intervention stating their reason
for intervention and invited interveners to present their evidence. Four (4)
parties registered as interveners in this application:
-
Government of PEI, as
represented by the Minister of Environment, Energy and Forestry;
-
PEI Senior Citizens'
Federation, represented by Mr. Roger King;
-
Environmental Coalition of
PEI (ECO PEI), represented by Mr. Matthew MacCarville; and
-
Mr. John te Raa, as a
private citizen.
[7] Commission staff
conducted two pre-hearing conferences with all parties participating. A
process for interrogatories, Company responses and filing of expert and
intervener evidence was agreed upon. The Commission website published all
information filed making the information available to all parties and the
general public.
[8] The public hearing
was held June 14, 2010 thru June 18, 2010 in the Commission's main hearing
room. The hearing participants included Mr. Spencer Campbell and Mr. Thomas
Laughlin, legal counsel for Maritime Electric, Mr. Gordon MacKay, legal
counsel for the Government of PEI, PEI Senior Citizens' Federation
represented by Mr. Roger King, Environmental Coalition of PEI represented by
Mr. Matthew MacCarville, and Mr. John te Raa, representing himself.
[9] Three groups—PEI
Federation of Agriculture, as represented by Mr. Ernie Mutch and Mr. John
Jamieson; National Famers Union Region 1 District 1, represented by Mr.
Elwin Wyand, Ms. Edith Ling, Mr. Douglas Campbell and Mr. David Best, and
Dairy Farmers of PEI, represented by Mr. Harold MacNevin—requested and
received permission to speak at the hearing. All three groups spoke on
behalf of the PEI farming community.
[10] There were members
of the media in attendance; however, few members of the public attended the
proceedings.
2. The Application
[11] The Company's original application filed with the Commission on January 29,
2010 requested approval of the following:
-
Rebasing of the Energy Cost
Adjustment Mechanism ("ECAM") which would increase the base charge for
energy incorporated into customer billings to $0.0940/kWh in 2010 and
$0.0960/kWh effective April 1, 2010;
-
Filing of an updated ECAM
rebasing report by November 30, 2010;
-
Continuation of the Point
Lepreau replacement energy deferral and approval of a 25-year amortization
of these deferred replacement energy costs beginning with the return to
service expected to be March 1, 2011; and
-
Approval of a maximum allowed
Return on Average Common Equity of 9.75 per cent for 2010 and 2011.
[12] The application incorporated the final step in the elimination of the second
block reduced rate, which was approved in 2008 by Commission Order
UE08-01
following a public process.
[13] As well, the Costs
Recoverable from Customers (Post 2003)—or ECAM—balance, excluding Point
Lepreau, is forecast to be $6,316,300 at the end of 2010 and
$8,800,000 at the end of 2011. The Point Lepreau replacement energy costs to
be recovered from customers, assuming a 25-year amortization beginning March
2011, would be $43,100,000 at the end of 2010 and $45,800,000 at the end of
2011.
[14] The application states there is no change requested in the monthly service
charge for the various rate categories. The company proposes the consumer
energy rate for electricity consumed will change from $0.1178 kWh for the
first 2,000 kWh/month and $0.0914 kWh for the remaining monthly consumption,
with a new combined rate of $0.1355 kWh month.
[15] The application would see the residential consumer using 650 kWh/month (or
7,800 kWh/year) experience a forecast annual electricity cost reduction of
(0.5%) and (0.4%) in 2010 and 2011.
[16] The Company stated the application contains just and reasonable proposals
which balance the interests of Maritime Electric and its customers and
allows the Company to provide a high level of service at prices which are
reasonable based upon their costs.
[17] On April 8 and 12, 2010 the Company filed supplemental affidavits requesting
the Commission approve an amended application which proposed:
-
A continuation of the 2,000
kWh/month 2nd energy block pricing;
-
Rebasing of the Energy Cost
Adjustment Mechanism ("ECAM") which would increase the base charge for
energy incorporated into customer billings to $0.0990/kWh effective August
1, 2010, and $0.0900/kWh effective April 1, 2011;
-
MECL file an updated report of
ECAM rebasing with the Commission by November 30, 2010;
-
A continuation of the Point
Lepreau replacement energy deferral and the approval of a 25-year
amortization of these deferred replacement energy costs beginning with the
return to service expected to be March 1, 2011; and
-
A maximum allowed Return on
Average Common Equity of 9.75 per cent for 2010 and 2011.
[18] Under this proposal the Costs Recoverable from Customers (Post 2003) or ECAM
balance, excluding Point Lepreau is forecast to be $7,758,500 at the end of
2010 and $12,467,600 at the end of 2011. The Point Lepreau replacement
energy costs to be recovered from customers, assuming a 25-year amortization
beginning March 2011, would be $43,294,100 at the end of 2010 and
$45,999,800 at the end of 2011. A Commission decision on the recovery of
Point Lepreau replacement energy is requested in this amended application as
well.
[19] The amended application states there is no change requested in the monthly
service charge for the various rate categories. The energy rate for
electricity is proposed to increase from $0.1178 kWh for the first 2,000
kWh/month and $0.0914 kWh for the remaining monthly consumption to $0.1455
kWh for the first 2,000 kWh/month and $0.1103 for the remaining monthly
consumption. The amended application maintains the same pricing relationship
between the second and first block rate.
[20] The amended application, as proposed, would see the residential
consumer using 650 kWh/month (or 7,800 kWh/year) experience a forecast
annual electricity cost reduction of (1.1%) in 2010 and no change in 2011
electricity costs over 2010.
[21] In addition, the amended application states the Revenue Requirement
Recovery associated with the second block reinstatement would be allocated
across all rate classes and adjustments would be made to the ECAM.
3. Discussion
3.1 Intervener—PEI Seniors Citizens' Federation
[22] The PEI Senior Citizens' Federation ("Seniors' Federation") presented
information concerning demographics of PEI seniors, the economic situations
many face in household budgets, and the increasing electricity cost
component which reduces available funds for other essential expenditures
such as food and shelter.
[23] The Seniors' Federation explained to the Commission seniors' energy
needs and the difficulties many face to achieve energy conservation.
[24] The Seniors' Federation raised the following financial issues with the
Commission:
-
It supports Maritime Electric's
objective to reduce customer debt;
-
The chosen solution of
increasing the basic rates by 15% for 2010 and a further 3% in 2011 is not
endorsed;
-
The majority of energy supply
costs are declining—future customer rates should be declining too;
-
NB Power set energy purchase
prices but customer rates are also dependent on Maritime Electric's
operating costs;
-
Increased scrutiny of Maritime
Electric's operating costs is required;
-
Maritime Electric continues to
request high annual capital expenditures and a high rate of return in a
non-growth, low risk business activity; and
-
Detailed future year estimates
are difficult to reason/check by public observers and customers.
[25] The Seniors' Federation notes that the basic electricity rate increase
applies to all rate tariff categories affecting every PEI resident, farmer
and business, and is independent of the second block issue. It also notes
that Maritime Electric is accumulating high customer debt during the Point
Lepreau refurbishment and future nuclear power will cost significantly more.
In addition, despite a static PEI energy demand situation and a Canadian
economy battling with decline, Maritime Electric proposes increasing annual
profits from $11.4 Million in 2009 to $12 Million in 2010 and $12.6 Million
in 2011.
[26] The Seniors' Federation expressed concern over the Point
Lepreau
refurbishment project, the continued delays and the mounting cost of
replacement energy which must be recovered from customers over future years.
They believe this recovery through rates, along with the unknown future
price of electricity from the nuclear generator, may make this an expensive
energy source.
[27] In addition, concern was expressed about the cost of power from the NB
Power Dalhousie generating facility which has increased substantially due to
fuel costs, and the future plans for the plant appear to be uncertain based
on public comments from NB Power.
[28] The Seniors' Federation made the following recommendations to the
Commission:
-
2010 rates remain unchanged
with the ECAM amortization period reduced to 8 months to contain customer
debt to the Company;
-
Return on Equity of 8% is
suggested which better reflects the operational risks of the Company;
-
A reduction in capital budget
to 8% of revenue to a maximum of $15 Million;
-
Have external consultants
review general and administrative expenses and generation asset costs;
-
Key Performance Indicators (KPIs)
should be set to competitive benchmarks;
-
Review viability of future
participation in Point Lepreau considering the energy replacement costs,
along with future energy costs from this source;
-
Direct the Company to consider
terminating its agreement with the Dalhousie generating facility; and
-
Future rate applications be
single year to enable timely rate changes each April.
[29] In response to Commission staff questioning during the hearing, the
Seniors' Federation stated they took no position on the elimination of the
second block even though many seniors are affected by this rate
differential.
3.2 Intervener—John te Raa
[30] Mr. John te Raa presented evidence to the Commission concerning
electric heating, its implications to the Company and to customers and
rates. Electric heating results in a poor system load factor, an indicator
of the efficiency usage of the electrical system. The higher the system
electrical load factor the more efficient the use of the system and the less
customer cross-subsidization of rates. For instance, Mr. te Raa provided
evidence which states the electric load factor of an oil heat customer is
64% while that of an electric heat customer is 30%. The Company's data,
provided through interrogatories, supports his claim that electric heat is
having a greater influence on PEI with last year's peak load almost shifting
to January from December.
[31] Mr. te Raa challenged the intervention by the Province of PEI which
supported the retention of the second block. In general, Mr. te Raa states
the Province is intervening to protect a small number of customers (7%) at
the expense (subsidization) of the majority of customers. In fact, Mr. te
Raa states low consumption customers, such as low income customers or
families on social services, pay higher electricity bills to offset the
discount provided to higher consumption customers.
[32] Mr. te Raa presented a proposal which would alter the current fee
structure so that higher energy usage customers would pay a higher base
service charge as a consequence of their impact on the system load factor
and capacity requirements during peak energy consumption periods. Mr. te Raa
stated the Commission should order the Company to create different rate
classes within the Residential Rate category as well as set up a different
rate class for electric heat customers, including those heating by heat
pumps.
[33] Mr. te Raa also stated the ECAM's objective is the smoothing of rates
within a set time frame and currently the ECAM just continues to grow and
defer the real cost of energy to customers while delaying the proper
customer price signals in rates. The ECAM rebasing in both the original
application and the amended application shows a growing ECAM deferral
account and is not operating as a rate smoothing mechanism.
3.3 Intervener—ECO PEI
[34] ECO PEI recommended the implementation of time-of-use rates and
suggested the initiative to replace mechanical meters with digital meters
should have taken advantage of the upgrade to install Smart meters. Smart
meters could be utilized in a variety of environmentally friendly
initiatives which ECO PEI believes have a direct benefit to customers. ECO
PEI suggests the utility become more involved in fostering future electrical
energy options which result in greater use of wind resources to heat our
homes, such as wind/electric thermal storage. Transportation was suggested
as a key focus for reducing Green House Gas ("GHG") emissions on the Island.
While other GHG emissions on the Island have decreased, emissions from
transportation have increased. ECOPEI suggested greater utilization of Grid
Enabled Vehicles and noted the absence of recharge stations for electric
vehicles.
[35] ECO PEI presented a variety of energy conservation and demand side
management initiatives and themes which looked at consumer energy usage
strategically over the longer term. Although their presentation did not
focus on the specifics of this application, ECO PEI would like further
development of smart grid and greater inter-regional cooperation in the
Maritimes which would assist in the development and usage of the PEI's
excellent wind resource.
3.4 Intervener—Government of PEI
[36] The Government of PEI, as represented by the Minister of Environment,
Energy and Forestry, presented the evidence and expert testimony of Laurence
Booth, Professor of Finance, Rotman School of Management, University of
Toronto. Mr. Booth has extensive experience in financial affairs and has
appeared before many regulatory boards providing evidence relating to Return
on Equity ("ROE") for Canadian utilities.
[37] Mr. Booth informed the Commission the objective of rate of return
regulation can be summarized as the "fair return standard" which has
received wide acceptance due to the legal precedent established in the 1929
case Northwestern Utilities v City of Edmonton. Mr. Justice Lamont's
definition of fair rate of return states:
"…that the company will
be allowed as large a return on the capital invested in the enterprise
as it would receive if it were investing the same amount in other
securities possessing an attractiveness, stability and certainty equal
to that of the company's enterprise."
[38] Economists, generally, refer to this principle as the opportunity cost
and it is generally agreed that the return is applied to the book value of
assets.
[39] Mr. Booth stated that most regulators in Canada have adopted an ROE
formula approach in which Capital Asset Pricing Model ("CAPM") has been the
predominant model used. The model is referred to as a risk positioning model
and it tries to estimate a fair return being the risk free rate, plus a risk
premium for the market and the company.
[40] Mr. Booth stated that utility stocks did not fair badly during the
recent financial market declines and have since regained their pre-market
crisis values. This is evidence of their low risk and the fair return
approved by regulators using this formula CAPM approach.
[41] Mr. Booth stated the returns of US utilities are not comparable as
these utilities are inherently riskier because the business climate in the
US is generally riskier. This is evidenced by the financial crisis which
originated in the US and the continued perilous economy there. He believes
the Canadian economic climate is much healthier in that the recession is
felt to be behind us and that Canadian government finances are much
healthier than the structural deficit problems faced by the US government.
[42] Mr. Booth stated that in 2009 regulators have reviewed the formula
results and made formula risk premium adjustments to take into consideration
the financial crisis of 2009. This has resulted in 2009 ROE decisions by
regulators being artificially high and these should come down as the
financial markets regain liquidity and stability.
[43] Mr. Booth describes the Company as a small distribution utility with a
low risk profile, as it is a monopoly provider on PEI, which is a low risk
environment due to no significant exposure to a single resource like
Newfoundland. Mr. Booth quotes an excerpt of the Standard & Poor's
assessment of the Company, "strong business profile … a mature, but stable
economy with relatively low growth rates." Mr. Booth makes reference to the
weakness of the Company being its small size, limited market access and
significant deferrals. Mr. Booth dismisses the deferrals due to regulators
ensuring their collection.
[44] Overall, Mr. Booth assesses the Company as a low risk Canadian utility,
even though it has a corporate rating of BBB+, its secured debt is rated at
A-. He indicates these ratings are below the averages for Canadian
utilities.
[45] Mr. Booth recommends an ROE of 8.0% at the 40% legislated common equity
ratio. In addition, he believes the legislated common equity ratio should be
revisited once the financial markets have settled from the financial crisis
of 2008/09.
[46] Mr. Wayne MacQuarrie, presented the PEI Government's position regarding
the retention of the 2nd block reduced rate. In his affidavit, Mr. MacQuarrie stated the Government initially supported the elimination of the
second block in 2008. However, due to changed circumstances, Government now
feels the second block should be retained until various issues associated
with electricity on PEI are resolved.
[47] Mr. MacQuarrie updated the Commission regarding ongoing Government
negotiations for less expensive energy supply from other jurisdictions such
as Quebec and Newfoundland. These suppliers are becoming viable options for
PEI with the Open Access Transmission Tariff ("OATT") approved by many
jurisdictions, and the development of a competitive energy supply market.
[48] Mr. MacQuarrie stated that the staged increase in the threshold for
2nd
block qualification has improved price signals to consumers and the
remaining consumers affected by the 2,000 kWh threshold have few viable
options to reduce energy consumption. In addition, the retention of the
second block at the current level will not result in a material change in
consumer consumption or financial consequence to all ratepayers.
[49] Mr. MacQuarrie stated the Point
Lepreau refurbishment and replacement
energy expense and the uncertainty associated with the Dalhousie generating
facility will have further rate burden on consumers and will impact energy
consumption decisions.
3.5 Members of the Public
[50] Each of the three groups that attended and made presentations at the
hearing expressed concern over electricity rates on PEI and their inability
to recover these rising costs from the market place. In addition, each group
expressed frustration over the Commission's previous decision to eliminate
2nd block reduced rate pricing. The farm groups stated that energy
conservation and demand side management programs have been incorporated in
their daily activities but farming operations require significant
electricity consumption. Many government programs, which provide assistance
for capital outlays to reduce farm energy bills, do not provide the
appropriate cost benefit relationship to warrant investment. For instance,
on-farm wind generated electricity requires changes in government
electricity regulations to allow for net billing. It is believed net billing
would provide a stronger business case as it results in a faster payback.
3.6 Applicant—Maritime Electric Company,
Limited
[51] Maritime Electric presented evidence and expert testimony of Kathleen McShane, President of Foster & Associates, an economic consulting firm. Ms.
McShane reiterated the fair return standard as the legal precedent upon
which regulators must establish ROE amounts. Ms. McShane states the fair
return standard gives a regulated utility the opportunity to:
-
earn a return on investment
commensurate with that of comparable risk enterprises;
-
maintain its financial
integrity; and
-
attract capital on reasonable
terms.
[52] Ms. McShane presented a view that Maritime Electric faces higher
business risk than the average Canadian utility. This assessment referenced
the following risk factors:
-
Maritime Electric faces higher
operating and supply risks relative to the typical Canadian distribution
utility. An Island location dependent upon submarine cables and the
requirement to maintain on-Island generation represents risks no other
Canadian distribution utilities face in regards to supply disruption;
-
PEI's
Renewable Energy Act
requires the Company to source 15% of its energy requirements from renewable
sources with an increase to 30% contemplated, and significant penalties for
non-compliance;
-
Maritime Electric's small size
and its limited potential for growth in serving a largely rural population
with low-growth rates puts pressure on the aging infrastructure and upward
pressure on rates;
-
Regulatory risk for the Company
has been a factor in the past noting the changed regulatory model to price
cap regulation and then back to cost-of-service regulation;
-
Maritime Electric continues to
maintain significant deferral accounts for energy purchases for both ongoing
energy supply and replacement of Point Lepreau energy due to the
refurbishment. These deferral accounts require regulatory approvals for
recovery and put pressure on the Company's financial position as evidenced
by the operating financial ratios;
-
Maritime Electric's corporate
credit rating of BBB+ is lower than that of the average Canadian electric
utility (A-) and the Standard & Poor's rating has noted the Company's poorer
business metrics, such as lower than average earning before taxes interest
coverage, funds from operation to total debt and challenged cash flow
position; and
-
Overall, Standard & Poor's have
rated Maritime Electric's business risk profile as "Satisfactory" which is
two rating categories below the average business risk profile assigned to
Canadian utilities of "Excellent".
[53] Ms. McShane concluded the ROE of 9.75% on a common equity ratio of
between 41% and 41.8% is not only reasonable but relatively low, based on
approved ROE levels for other Canadian and US utilities.
[54] Ms. McShane acknowledged the role of formulas in ROE rate setting,
however, she pointed to shortcomings in the formula approach in that
measuring individual securities risk relative to the market is by a beta
factor. Selecting a beta factor that appropriately measures security risk
requires judgment that can lead to disagreement among evaluators. Ms.
McShane suggested no one formula can measure all requirements of the fair
return standard and pinpoint a fair return. In establishing a fair return,
reliance on multiple tests, such as, CAPM, discounted cash flow and
comparable earnings tests, is a better approach. Each test requires judgment
in their application.
[55] Ms. McShane stated that this Commission has never adopted the CAPM
formula as the means of ROE. Ms. McShane also stated the Commission has
previously taken into consideration comparable earnings of other Atlantic
Canadian electric utilities in setting ROE.
[56] Ms. McShane agreed that certain Canadian regulators have incorporated
premiums in ROE to account for the impact of the financial crisis. Ms.
McShane argued that the financial crisis has highlighted the flaw of the
automatic formula approach as the formulas do not take into account all
business risks in a timely fashion.
[57] Ms. McShane provided a table of approved ROE and common equity ratios
for 2009. This table also provided US average ROE as well. The table
outlines the 2009 average Canadian ROE of 9.52% with a common equity ratio
of 40.5%. This includes the 9.85% ROE for Ontario Electricity Distributors
for 2010. This 2010 OEB decision is 0.10% higher than the 2009 rate of
9.75%.
[58] In support of the written evidence filed as part of the application,
Maritime Electric provided testimony from Company President, Mr. Fred
O'Brien and a panel of members of Senior Management, consisting of: Mr.
William Geldert, Mr. John Gaudet and Mr. Steve Loggie.
[59] Maritime Electric provided the Commission with a supplemental affidavit
in support of retaining the second block in its current form for the
following reasons:
-
It may be premature due to
ongoing discussions between the Governments of Quebec and PEI concerning a
power purchase agreement which would reduce energy costs and could affect
decisions concerning the elimination of the second block;
-
Current DSM initiatives have
been successful and the retention of the 2nd block will not have a material
impact upon future Company DSM plans; and
-
The retention of the second
block does not cause material differences in the financial situation of the
Company as the Revenue Requirement Recovery or revenue shortfall from the
2nd block will be spread across all rate classes, and these differences are
not material.
[60] In addition, in response to comments raised during the hearing on the
issue of net billing, the Company expressed concerns relating to
cross-subsidization of ratepayers under net billing approaches.
[61] The Commission acknowledges and thanks all of the participants for
their contributions.
4. Findings
[62] Upon completion of the public hearing and a review of the evidence and
closing submissions of the parties, the Commission made the following
determinations:
4.1 Point Lepreau Replacement Energy
[63] The Company has a 4.72% participation agreement with NB Power Nuclear
which entitles the Company to this portion of energy output from the
facility. During the hearing the Commission heard the Company had little
influence on the refurbishment decision due to its minor involvement with
the facility. The 1994 participation agreement established the requirement
to pay the monthly fixed overhead costs of the facility during
refurbishment, as well as obtain replacement energy.
[64] During the hearing, the Company stated that future participation in
Point Lepreau is more beneficial than trying to buy out its participation
agreement responsibilities. The Company stated the Lepreau generating
facility is still economically viable, in their opinion.
[65] Maritime Electric stated NB Power has not made any decisions regarding
the customer rate recovery of replacement energy costs. While Maritime
Electric is deferring the replacement energy costs it continues to make
monthly payments to NB Power for its share of the operating and maintenance
costs.
[66] At present, the refurbishment of Point
Lepreau is not complete and
there have been several delays. The expected date of return to service is
now scheduled as March 1, 2011; however, further delays are possible.
[67] The Commission heard the concerns expressed by both the Seniors'
Federation and Mr. te Raa regarding the increasing deferred replacement
energy costs. Effective January 1, 2009, and continuing to the return to
service date of Point Lepreau, the Commission directed the deferral of
replacement energy costs. The Company's application states the 2010 year-end
balance of replacement energy costs are forecast to be $43.3 million and
$46.0 million in 2011. This assumes a return to service of March 1, 2011 and
the beginning of the 25-year amortization period requested in this
application.
[68] The Commission has considered the information filed with the
application concerning the amortization of replacement energy costs of other
jurisdictions and notes that it is accepted regulatory practice to amortize
costs over the future service life of the refurbished facility.
[69] The Commission, therefore, orders the Company to continue with the
deferral of the replacement energy costs until the return to service of the
Point Lepreau facility. The Commission further orders the Company to begin
recovering replacement energy costs through rates over the expected future
service life of the facility, currently estimated to be 25 years. The
Commission directs the Company to provide updated information concerning the
expected future service life once reliable estimates are established.
[70] The Commission is concerned over the lack of detailed evidence
associated with the Point Lepreau facility. The Commission directs Maritime
Electric to file, on a confidential basis, the cost estimates and economic
analysis associated with their continued involvement with the facility.
4.2 ECAM Rebasing and Amortization Period
[71] The Company has filed the ECAM rebasing proposal contained in this
application pursuant to Commission Order
UE09-02. The Company's ECAM
balances in the original application and amended application are forecast as
follows:
|
Calendar Year |
ECAM Year End Balance |
Original Application |
2010 |
$6,122,255 |
2011 |
$8,600,141 |
Amended Application
(retain 2nd block) |
2010 |
$7,758,524 |
2011 |
$12,467,603 |
[72] The original application and supplemental amended application (retain
2nd block) contained ECAM rebasing proposals that had the following annual
customer cost impact:
|
2010 |
2011 |
Rate Class |
Demand
KW/Month |
Consumption
kWh/Month |
Original
Application
Apr 1 |
Amended
(Retain
2nd Block)
Aug 1 |
Original
Application
Apr 1 |
Amended
(Retain
2nd
Block)
Aug 1 |
Residential
- Rural |
n/a |
650 |
-0.5% |
-1.1% |
-0.4% |
0.0% |
|
|
|
|
|
|
|
General
Service |
0-20 |
500 |
2.1% |
2.7% |
0.5% |
0.8% |
General
Service |
30 |
3,000 |
2.1% |
2.7% |
0.5% |
0.8% |
General
Service |
50 |
5,000 |
2.2% |
2.7% |
0.4% |
0.7% |
General
Service |
250 |
250,000 |
-2.7% |
-2.1% |
-1.6% |
-1.3% |
|
|
|
|
|
|
|
Large
Industrial |
9,000 |
9,000,000 |
-9.3% |
-9.0% |
-5.3% |
-4.9% |
|
|
|
|
|
|
|
Small
Industrial |
50 |
5,000 |
2.0% |
2.6% |
0.3% |
0.6% |
Small
Industrial |
150 |
25,000 |
0.0% |
0.5% |
-0.5% |
-0.2% |
Small
Industrial |
500 |
300,000 |
-4.5% |
-3.9% |
-2.6% |
-2.2% |
[73] The amended
application, with the retention of the 2nd block, incorporates an ECAM base
energy charge of $0.0990/kWh effective August 1, 2010 and $0.0900kWh
effective April 1, 2011.
[74] The Commission
shares the concerns over the extent of deferrals for both replacement energy
and normal energy supply. Interveners noted that in the amended application
the Company ended up increasing the deferred energy charges. The Commission
notes that, in addition to increasing the deferrals, the annual customer
cost impact increased only slightly with the final result for 2011 being
rural residential customers seeing no change in annual cost of electricity.
[75] In response to
intervener and Commission questions, the Company stated their desire to
eliminate deferred energy accounts and recover all costs from customers
sooner. However, the Company stated their additional concern regarding the
cost impact to customers. The Company's amended application was an attempt
to balance the Company's interests, as well as the cost to customers, while
maintaining the second block.
[76] The Commission is
concerned by the mixed signals sent to all parties in the amended
application. The base ECAM rate would be set at a rate that results in the
deferred ECAM account increasing in value. This places further burden on
future ratepayers who will ultimately cover these costs.
[77] Most interveners
agreed that energy charges should reflect the true supply cost of energy and
this would send the appropriate price signals to consumers regarding energy
choices. In addition, the Commission heard that the overall cost of energy
is important to seniors and this group wants an indication that energy rates
are stabilizing. A reducing ECAM deferral balance is a step in that
direction.
[78] The Commission has
reviewed various ECAM rate scenarios and orders that the new base rate for
ECAM be set at $0.0970kWh effective August 1, 2010 and that an additional
$0.006kWh be added to the ECAM base rate for the period August 1, 2010 to
December 31, 2010. This additional rate allows for recovery of energy costs
associated with the delay in the rate application from the initially
requested April 1, 2010 implementation date to the August 1, 2010 actual
implementation date.
[79] The new ECAM base
rate is forecast to result in year-end ECAM deferral account balances of
$6,046,954 for 2010 and $5,709,184 for 2011. These balances are lower than
both the original and amended applications. The new ECAM base rate will
result in a year-over-year annual rural residential cost change of -0.2% in
2010 and 1.1% in 2011, assuming exchange rates and energy supply costs
remain consistent with 2010 levels. The Commission considers this an
appropriate rate change to achieve reduced deferrals.
[80] The Commission has
considered the request from the Seniors' Federation to reduce the ECAM
amortization period and increase the collection of deferred energy supply
costs. The Seniors' Federation views this as more desirable than an increase
in base rates as it would permit the rates to easily reduce if energy supply
costs decrease. The Commission has considered this option and notes that the
ECAM at one time was set at eight months; however, feels it is more
important to have the ECAM base rate set at a level close to the actual
energy supply costs, so that deferred energy costs are minimal into the
future. Both the ECAM and the base rates are subject to regulatory control
and can be adjusted to reflect reduced energy costs. Therefore, the
Commission directs the Company to continue the 12-month amortization in the
ECAM formula.
4.3
2nd Block Tariff and Rate Design
[81] The Company filed a supplemental affidavit amending the original application
and requesting reconsideration of Commission Order
UE08-01. This Order
approved the elimination of the second block rate over a three-year period.
Although the Company is not financially impacted by the second block
elimination, Maritime Electric stated that the circumstances regarding
energy negotiations and their potential implications to the overall rate
tariff, as well as progress on demand side management programs support the
request for reconsideration.
[82] The Commission heard from farm groups concerning the financial impact
of this rate elimination. These groups discussed their limited ability to
reduce energy consumption within existing demand side management tools. In
addition, current government programs, designed to financially assist farms
install on-farm renewable generation, fall short in making a sound business
case for the investment. Farm groups suggested that legislation and
regulation changes are required by Government to improve the attractiveness
of on-farm renewable energy infrastructure.
[83] The Commission was informed of the peculiarities which exist in the
current rate tariff schedule. The current tariff schedule was forced on the
Company with the legislated price cap regulation of 1994. For instance,
within the residential rural tariff (and 2nd block discount) the following
are some organizations which qualify:
-
small and large scale farm
organizations,
-
fish farms,
-
campgrounds and trailer parks,
-
hotels, motels and tourist
courts,
-
credit unions, and
-
services incidental to fishing
and farming.
[84] The Commission was informed by Company officials during the hearing
that the tariff schedule which existed prior to 1994 was completely
different with consideration given to the volume and nature of electricity
usage. For instance, rate differences existed between 100 amp and 200 amp
service.
[85] The Commission heard from Mr. John te Raa concerning the system
efficiency implications of electric heat and apparent cross-subsidization of
rates and charges between low- and high-energy usage customers. Mr. te Raa
states the 2nd block tariff furthers this inequity. Mr. te Raa directed the
Commission to the results of the 2008 Cost of Service Study filed as a
response to a Government of PEI interrogatory in this application. This
study highlights inequities between rate classes within the current tariff
structure.
[86] During the hearing, Company officials acknowledged the results of the
2008 Cost of Service Study and advised the Commission that to consider the
2nd block rate issue in isolation of the other obvious inequities in the
overall tariff structure would be unreasonable and unfair to all customers.
[87] The Commission noted Company comments which stated that a new cost of
service study and a rate design proposal with a goal of tariff fairness
within ranges is required.
[88] The Commission notes the preamble to the
Electric Power Act which
states: "Whereas the rates, tolls and charges for electric power should
be reasonable, publicly justifiable and not discriminatory".
[89] This preamble instructs the Commission to ensure fairness within rate
categories and that rates must be based on the cost of providing this
service. That means rates do not take into consideration the characteristics
of the customer such as farming, fishing, home heat or industrial usage.
Rates developed with a rate design objective of fairness based on cost of
service are the requirements of the legislation.
[90] The Commission appreciates that the farm community has faced
significant economic challenges, but that fact alone does not permit the
Commission to vary rates to assist that industry. In order to achieve rate
fairness, rates must be based on the cost of providing service to a customer
or class of customers.
[91] In true cost of service terms, the Commission was not presented with
evidence that warrants retention of the declining 2nd block rate. However,
evidence was heard that the residential rate class itself is seriously
flawed. Adopted in 1994 from the NB Power rate structure, this rate
structure is out of date.
[92] The Commission accepts the argument that any further changes to rate
tariffs should await the outcome of a new rate design proposal based on a
full cost of service study.
[93] Therefore, the Commission will defer the decision on the removal of the
2nd block tariff until a rate design proposal is approved by the Commission.
The Commission orders the Company to prepare a complete rate design proposal
with all the necessary supporting reports. The Commission has heard evidence
that a new rate design process could result in some significant rate
changes, both increases and decreases, for customers. Upon completion of the
cost of service and rate design process, the Company is encouraged to engage
in stakeholder consultations which explain the process and gain input on the
proposed rate classifications. The rate design proposal will incorporate
recommendations on the current 2nd block and any other potential rate
additions or deletions. Further, the Commission directs that the impact of
the increased use of electric heat on the system service requirements be
separately considered and addressed in the rate design process.
[94] The rate design proposal must be filed with the Commission by December
31, 2011. This date provides time for the conclusion of inter-governmental
power purchase agreement negotiations.
4.5 Rate of Return
[95] Maritime Electric is requesting approval of a 9.75% return on average
common equity. Maritime Electric states iness risk
than other Atlantic Canada investor-owned electric utilities s it operates
on a small island with an undiversified economy. The inability to spread
risk throughout a diversified customer base means investors are more
cautious on the outlook for Maritime Electric. The Company states this is
evidenced by the Standard and Poor's BBB+ credit rating which indicates a
stable outlook, but this rating is lower than other investor-owned utilities
such as Emera's, Nova Scotia Power, and Newfoundland Power. In fact,
Maritime Electric notes Standard and Poor's expressed concern about Maritime
Electric's relatively poor cash flow position which is caused by the ECAM
and delayed recovery of energy costs. The bond raters expressed concern
about the relatively low earnings as a percentage of debt ("Interest
Coverage Ratio").
[96] Section 24(1) of the
Electric Power Act states return on investment
shall be set by the Commission and reads as follows:
Return on investment,
utility authorized to earn certain, computation of |
24. (1) Every public
utility shall be entitled to earn annually such return as the
Commission considers just and reasonable, computed by using the rate
base as fixed and determined by the Commission for each type of
service furnished, rendered or supplied by such public utility, and
the return shall be in addition to the expenses as the Commission
may allow as reasonable and prudent and properly chargeable to
operating account, and to all just allowances made by the Commission
according to this Act and the rules and regulations made by the
Commission hereunder. |
[97] The Commission heard from expert witnesses who stated the principles of
the fair return standard. In essence, a fair return is met if a utility can
attract capital on reasonable terms, can maintain its financial integrity,
and the return allowed is consistent with returns of businesses with similar
risks. That standard was first established in Canada with the 1929 case,
Northwest Utilities v. Edmonton (City).
[98] The Commission noted Mr. Booth's comments in which he stated the 2009
approved ROE was adjusted higher to take into consideration the 2008-2009
financial crisis. In fact, Mr. Booth suggested the Cost of Capital Review,
by the Ontario Energy Board (OEB), was a consequence of the financial
crisis. The Commission noted this decision was made after the economic
financial problems and reflects the improved Canadian economy.
[99] The Commission noted testimony from both experts with different
opinions regarding the risk profile of Maritime Electric in comparison to
the Ontario distribution utilities. The Commission accepts that Maritime
Electric, with its responsibilities for electricity supply, is different
than Ontario electric distribution utilities. The Commission views this
difference as significant.
[100] The Commission notes the lower than average Company corporate rating
prepared by Standard & Poor's and the debt rating of BBB+, both lower than
Canadian averages, is further evidence that the risk profile of Maritime
Electric is higher.
[101] The Commission notes the 2009 Nova Scotia Power ROE, arising from a
negotiated settlement agreement, of 9.35% on a common equity ratio of 37.5%.
In addition, the Newfoundland Power ROE of 9.0% with a common equity ratio
of 45% was approved for 2010.
[102] The Commission also notes decisions from the British Colombia Utilities
Commission ("BCUC") regarding the ROE rates allowable for a benchmark
utility (9.5%), Terasen Gas. In addition, as pointed out by Ms. McShane in
her evidence, the BCUC decision stated:
"The Commission Panel
notes that CAPM is based on a theory that can neither be proved nor
disproved, relies on a market risk premium which looks back over nine
decades and depends on a relative risk factor of beta. The fact that the
calculated beta for PNG (considered by Dr. Booth to be the most risky
utility in Canada) was 0.26 in 2008 causes the Commission Panel to
consider that betas conventionally calculated with reference to the S&P/TSX
are distorted and require adjustment. The Commission Panel will give
weight to the CAPM approach, but considers that the relative risk factor
should be adjusted in a manner consistent with the practice generally
followed by analysts so that it yields a result that accords with common
sense and is not patently adsorb."
[103] The Commission finds this commentary particularly relevant. The
Commission did not adopt a formula approach to ROE during a period of time
when such an approach was used by regulators as the standard for setting
ROE. The Commission sees little value in placing greater emphasis on a
formula approach at a time when that approach is either being abandoned,
altered or deviated. Judgement, taking into consideration comparators,
current market conditions, and appropriate risk assessment, are also very
relevant.
[104] The Commission notes the BCUC ROE decision for FortisBC of 9.75%, which
is 0.25% above the benchmark BC ROE rate. This Commission views Maritime
Electric as a higher risk than the benchmark BC utility and FortisBC due to
a variety of factors such as utility size, nature of operations, economic
climate within which it operates, and regulatory risk factors.
[105] Taking into consideration all the ROE evidence presented, the
Commission finds an ROE of 9.75% to be fair and reasonable considering the
risk factors of Maritime Electric, the allowed ROE of comparable regional
and national jurisdictions, and the corporate business and debt ratings of
Maritime Electric.
4.4 Revenue Requirement and Other Matters
[106] The rates of a public utility are designed to generate, in a
fiscal year, what is known as the revenue requirement. The revenue
requirement is the sum of all operating expenses, amortization or
depreciation of capital assets, interest on debt, income tax and return on
equity. Under traditional rate regulation, the revenue requirement approval
is required to establish customer rates.
[107] With the establishment and approval of the ECAM approach to rate
setting, the energy cost component of the revenue requirement is essentially
established each month as the energy rates are set based on actual costs
incurred by the company, plus or minus the net ECAM adjustment. The
Commission assesses the Company's due diligence in obtaining the best price
for energy supply. During the 2009 rate case, the evidence of Mr. Terry
MacDonald, who reviewed the current Energy Purchase Agreements and provided
energy pricing advice to the Commission, supports this information. As these
same agreements are in place until March 2011, the Commission, therefore,
accepts the energy supply costs of the Company as reasonable until that
time.
[108] The remaining costs comprising the revenue requirement are
assessed by the Commission for reasonableness. The
Electric Power Act
provides guidance to the Commission in Section 21(3) which reads:
Rate base,
determination and fixing for each utility |
21. (1) The
Commission may . . .
(3) (a) include all
or any of
(i) an allowance
for necessary working capital, and
(ii) any other fair
and reasonable expenditure which the Commission thinks proper and
basic to the public utility's operation; |
[109] Expenditures of Maritime Electric are reviewed by the Commission
monthly along with rate schedules. In addition, the rate application
includes details of annual expenditure plans. The Commission has considered
these estimates of expenditures using analysis and comparison of past
expenditures and inquiries into proposed plans for future expenditures. In
addition, the public hearing provided an opportunity for further review into
the reasonableness of the expenditures.
[110] The Seniors' Federation expressed concern about the oversight of
Company operations and expenses in both the generation, general and
administrative areas. In addition, they stated the current Key Performance
Indicator ("KPI") monitoring tool employed by the Commission lacked
credibility in that no external comparators are considered. The Commission
acknowledges the shortcomings of the KPI measurement tool but views the
process as valuable. The Commission notes there must be caution exercised in
comparing organizations both within the utility sector and general business
community. Considerable judgment must be exercised in the KPI review
process. The Commission is involved in the process of benchmarking
evaluation techniques, an issue currently being debated within the
regulatory community across Canada.
[111] The Commission understands the concerns raised by the Seniors'
Federation regarding Commission oversight of Company management and
operations. While not always highly visible, this is a constant function of
the Commission and a consideration woven into all interactions between the
regulator and the utility. In addition, external expertise and consultants
are employed from time to time to assist the Commission in this regard.
[112] Recent engagements by the Commission include: propriety of general and
administrative expenses; assessment of power purchase contracts; demand side
management plans; open access transmission tariff requirements, and the
health and safety impacts of transmission lines.
[113] The Commission endeavors to make all such assessments available to the
public, however, given the confidential nature of some matters, not all
reviews are made public.
[114] The Commission, in its duty to ratepayers, must also be mindful of the
costs of employing such expertise and satisfy itself that there is value to
the Commission and ratepayers in such expenditures. The Commission, through
normal regulatory processes, also affords the opportunity for interested
parties to pose questions and raise concerns.
[115] The Seniors' Federation expressed concern about the value of Company
capital expenditures and the implications for rates. All capital
expenditures are approved by the Commission through a public process. The
Company is required to provide detailed explanations for all proposed
capital expenditures. The Commission not only questions company proposed
initiatives, but also considers matters that should be explored. For
example, following the Hurricane Juan damage in Nova Scotia, the Company was
instructed to prepare and file a Contingency Readiness and Emergency
Response Plan which covers a variety of contingencies such as submarine
cable failures, transmission tower system failures, Emergency Response Plans
and an Infrastructure Readiness Report. This initiative proved valuable when
the 2008 ice storms caused considerable damage to transmission and
distribution systems.
[116] The Seniors' Federation suggested a capital budget of 8 to 12% of
revenue to a maximum of $15 Million, which would have the impact of reducing
capital expenditures by $7 Million this year. The Commission places high
value on system reliability and is concerned an artificial cap on capital
expenditures might jeopardize necessary capital upgrades. Given the scrutiny
of capital budgets and the necessary approval process, the Commission is not
prepared to endorse such a cap.
[117] The Commission considers its website a valuable tool for providing
information to the public and will continue to post relevant information to
the site. The Commission will continue with the current capital budget
approval process.
5. Disposition
[118] An Order will therefore issue implementing the findings and
conclusions contained in these reasons.
Order
UPON receiving an application by
Maritime Electric Company, Limited for approval of proposed amendments to
its rates, tolls and charges;
AND UPON
receiving a supplemental affidavit amending the original application to
request reconsideration of the elimination of the 2nd block
tariff;
AND UPON
reviewing the additional evidence received in response to staff
interrogatories and intervener interrogatories;
AND UPON
reviewing and taking into consideration the evidence provided during the
hearing by interveners and expert witnesses;
AND UPON
review of previous Commission Orders concerning the Energy Cost Adjustment
Mechanism (ECAM), Rate of Return, Point Lepreau replacement energy and 2nd
block tariff elimination;
NOW THEREFORE,
for the reasons given in the annexed Reasons for Order;
IT IS ORDERED THAT
1. the Company
shall continue deferral of Point Lepreau replacement energy costs until
its return to service at which time the Company will begin amortization
of this cost, through the ECAM account, over the future expected service
life of the refurbished facility;
2. the Company
shall file a business case analysis associated with its continued
involvement for both Point Lepreau and Dalhousie generating facilities;
3. the Company
shall rebase the base rate of energy effective with meter readings taken
on and after August 1, 2010 as follows:
|
August 1,2010 |
Additional Rate August
1, 2010 to
December
31, 2010 |
ECAM Base Rate ($/kWh) |
0.0970 |
0.006 |
4. the Company
shall continue with a 12-month amortization period in the ECAM formula;
5. the maximum
allowed return on average common equity is set at 9.75% for 2010 and
2011; and
6. the Company
shall retain the 2,000 kWh second block reduced rate and include
consideration of this issue in a rate design proposal to be filed with
the Commission by December 31, 2011.
DATED
at Charlottetown, Prince Edward Island, this 12th day of July, 2010.
BY THE COMMISSION:
Maurice
Rodgerson, Chair
John Broderick, Commissioner
Anne Petley, Commissioner
Ernest Arsenault, Commissioner
Notice:
Section 12 of the
Island Regulatory and Appeals Commission Act
reads as follows:
12. The Commission
may, in its absolute discretion, review, rescind or vary any order or decision made by it,
or rehear any application before deciding it.
Parties to this proceeding seeking a review of the
Commission's decision or order in this matter may do so by filing with the Commission, at
the earliest date, a written Request for Review,
which clearly states the reasons for the review and the nature of the relief sought.
Sections 13.(1),
13(2), 13(3), and 13(4) of the
Act provide as follows:
13.(1) An appeal lies from a decision or order of
the Commission to the Court of Appeal upon a question of law or
jurisdiction.
(2) The appeal shall be made by filing a notice of
appeal in the Court of Appeal within twenty days after the decision or
order appealed from and the rules of court respecting appeals apply with
the necessary changes.
(3) The Commission shall be deemed to be a party to
the appeal.
(4) No costs shall be payable by any party to an
appeal under this section unless the Court of Appeal, in its discretion,
for special reasons, so orders.
NOTE:
In accordance with IRAC's Records
Retention and Disposition Schedule, the material contained in the official
file regarding this matter will be retained by the Commission for a period
of 5 years.