UE21505 – MECL Application to Collect Operating and Capital Costs Related to Hurricane Fiona
- Notice of Application – Seeking Approval to Increase Electricity Rates to Collect Additional Operating and Capital Costs Related to Hurricane Fiona Damages – November 21, 2023
- MECL Application for Recovery of Fiona Restoration Costs – November 2, 2023
- Order UE 22-08 – Interim Approval for Hurricane Fiona Deferral – December 19, 2022
Exhibit List
Applicant Exhibits
- Exhibit M-1 – MECL Interim Approval to Defer Costs for Hurricane Fiona – November 25, 2022
- Exhibit M-2 – MECL Interrogatory responses to Commission Staff re. Fiona – December 13, 2022
- Exhibit M-3 – MECL Interrogatory responses to Commission Staff re. Fiona – December 15, 2022
- Exhibit M-4 – Hurricane Fiona Post Mortem Report – January 31, 2023
- Exhibit M-5 – Refiled Hurricane Fiona Post Mortem Report – March 7, 2023
- Exhibit M-6 – MECL Application for Recovery of Fiona Restoration Costs – November 2, 2023
- Exhibit M-7 – MECL Interrogatory responses to Roger King – January 19, 2024
- Exhibit M-8 – MECL Interrogatory responses to Edward Robillard – January 19, 2024
- Exhibit M-9 – MECL Response to Intervener Application – January 26, 2024
- Exhibit M-10 – MECL Interrogatory Response to Edward Robillard – February 1, 2024
- Exhibit M-11 – MECL Interrogatory Response to Roger King – February 1, 2024
- Exhibit M-12 – MECL Requests Extension Filing Interrogatory Responses – July 5, 2024
- Exhibit M-13 – MECL Responses to EA Technologies Interrogatories Re. Fiona – July 26, 2024
- Exhibit M-13(a) – MECL Responses to EA Technologies Interrogatories – CONFIDENTIAL
- Exhibit M-13(b) – Appendix B – CONFIDENTIAL
- Exhibit M-13(c) – Appendix E – CONFIDENTIAL
Commission Exhibits
- Exhibit C-1 Interrogatories from Commission staff to MECL – December 8, 2022
- Exhibit C-2 Letter of Direction from Commission to MECL Re. Fiona Report – December 8, 2022
- Exhibit C-3 Interrogatories from Commission Staff to MECL – December 15, 2022
- Exhibit C-4 Letter of Direction from Commission to MECL Re. Fiona Report – February 7, 2023
- Exhibit C-5 Letter to Energy Democracy Now re. Fiona Request to Intervene – February 1, 2024
- Exhibit C-6 Interrogatories from EA Technology to MECL Re. Fiona Application – June 12, 2024
Energy Democracy Now! Co-operative Limited
- Exhibit E-1 Application for Intervener Status – December 11, 2023
- Exhibit E-2 Revised Application for Intervener Status – December 21, 2023
Public Exhibits
- Exhibit P-1 Comments from Roger King to Commission re. Fiona Deferral request – December 13, 2022
- Exhibit P-2 Comments from Wally Bambrick to Commission re: MECL Fiona Application – November 28, 2023
- Exhibit P-3 Comments from Peter McMurchy to Commission re: MECL Fiona Application – December 12, 2023
- Exhibit P-4 – Interrogatories from Edward Robillard to MECL Re. Fiona Application – January 2, 2024
- Exhibit P-5 – Interrogatories from Roger King to MECL Re. Fiona Application – January 5, 2024
- Exhibit P-6 – Additional Interrogatories from Edward Robillard to MECL Re. Fiona Application – January 16, 2024
- Exhibit P-7 – Additional Interrogatories from Roger King to MECL Re. Fiona Application – January 21, 2024
- Exhibit P-8 – Comments from Edward Robillard to Commission Re. Fiona Application – January 25, 2024
- Exhibit P-9 – Comments from Roger King to Commission Re. Fiona Application – January 26, 2024